RERA’d by NeevHQ

Projects · MANGLAM MULTIPLEX PRIVATE LIMITED

M3M ROUTE65

Manglam Multiplex · Sector 65, Gurugram

Registered with RERA: Mar 2024

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Manglam Multiplex

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameM3M ROUTE65
Builder (promoter)MANGLAM MULTIPLEX PRIVATE LIMITED
LocationVILLAGE MAIDAWAS, SECTOR-65, GURUGRAM, HARYANA
RERA project IDRERA-GRG-1548-2024
Registration certificate numberGGM/803/535/2024/30 DATED 27.03.2024
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/02/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area4.00 acres
Licence84 of 2022 dated 06-07-2022 and 213 of 2023 dated 20-10-2023
Estimated cost of the project₹39,232.81 lakh (₹392.33 crore)
Total units (plots, apartments, shops)808
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered534
Units unsold when registered274
Layout plan approved on12-02-2024
Building plans approved on12-02-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date28-02-2027
Revised completion date28-02-2027
Infrastructure: projected completion30-06-2026
Infrastructure: percentage complete when registered10%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2026 (JAN-MAR)
Latest report submitted on14-Apr-2026
Quarterly reports listed on the portal8

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹2,203.59 lakh (₹22.04 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹367.62 lakh (₹3.68 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹478.35 lakh (₹4.78 crore)
Project bank account (escrow): deposited in the quarter₹2,203.59 lakh (₹22.04 crore)
Project bank account (escrow): withdrawn in the quarter₹2,222 lakh (₹22.22 crore)
Project bank account (escrow): balance at quarter end₹34.78 lakh (₹0.35 crore)
Units in the project (apartments / plots)808 apartments
Sold in the quarter16 apartments
EDC (development charges): paid / due as on date₹2,660.12 lakh (₹26.6 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 12-02-2024
  • Zoning Plan: Obtained Approval 09-02-2024
  • Service Plans: Obtained Approval 23-04-2024
  • Electricity Plans: Obtained Approval 31-01-2024
  • Site Plans: Obtained Approval 12-02-2024
  • Building Plans: Obtained Approval 12-02-2024
  • Fire NOC: Obtained Approval 20-03-2024

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 02 Apr 2026, for January to March 2026
By part
  • Sub structure: 100%
  • Super structure: 100%
  • MEP - Mechanical: 100%
  • MEP - Electrical: 100%
  • MEP - Plumbing & Firefighting: 100%
  • Finishing - Internal: 100%
  • Finishing - External: 100%
Unclear in the certificate
  • The certificate covers the whole M3M Route65 commercial project (808 units) and does not name separate towers or blocks. Figures are project-wide cumulative values.
  • The percentages shown are for cumulative work done till date. The certificate does not give a separate overall percentage for work done in the quarter.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against MANGLAM MULTIPLEX PRIVATE LIMITED (all its projects)61 (Complaint: 52; Compensation: 9)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026