M3M Soulitude 3

Aawam Residency · Sector 89, Gurugram

Registered with RERA: May 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Aawam Residency

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameM3M SOULITUDE 3
Builder (promoter)AAWAM RESIDENCY PRIVATE LIMITED
LocationSECTOR 89, GURUGRAM
RERA project IDRERA-GRG-1897-2025
Registration certificate numberGGM/952/684/2025/55 DATED 21.05.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/03/2029
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.85 acres
Licence- 102 of 2022 dated 27.07.2022 License No- 32 of 2021 dated 03.07.2021
Estimated cost of the project₹10,766.42 lakh (₹107.66 crore)
Total units (plots, apartments, shops)128
Unit sizes (carpet area, as declared)4 units of 503 sq ft carpet; 12 units of 533 sq ft carpet; 8 units of 565 sq ft carpet; 4 units of 597 sq ft carpet; 16 units of 609 sq ft carpet; 12 units of 611 sq ft carpet; 36 units of 617 sq ft carpet; 8 units of 685 sq ft carpet; 8 units of 754 sq ft carpet; 4 units of 760 sq ft carpet; 4 units of 781 sq ft carpet; 12 units of 925 sq ft carpet
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on10-03-2025
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-04-2025
Likely completion date31-03-2029

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal5

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹58.48 lakh (₹0.58 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹597.12 lakh (₹5.97 crore)
Spent on construction of apartments in the quarter₹656.95 lakh (₹6.57 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0.17 lakh (₹0 crore)
Project bank account (escrow): deposited in the quarter₹58.48 lakh (₹0.58 crore)
Project bank account (escrow): withdrawn in the quarter₹60 lakh (₹0.6 crore)
Project bank account (escrow): balance at quarter end₹0.83 lakh (₹0.01 crore)
Units in the project (apartments / plots)128 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹83.73 lakh (₹0.84 crore) paid; ₹83.73 lakh (₹0.84 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 25-01-2023
  • Electricity Plans: Obtained Approval 09-11-2022
  • Site Plans: Obtained Approval 28-03-2025
  • Building Plans: Obtained Approval 28-03-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 01 Oct 2026, for July to September 2026
By part
  • Residential Independent Floor 32 Plots 128 Units: Table A component progress, as % of total proposed work: sub structure 43%, super structure 40%, mechanical MEP 19%, electrical MEP 12%, plumbing and firefighting 15%, internal finishing 10%, external finishing 9%. Site inspection done on 30 Sep 2026.
Unclear in the certificate
  • Table A lists a single building entry without a separate tower number; no single overall percentage is stated.
  • The Pile row under laying of foundation is blank.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against AAWAM RESIDENCY PRIVATE LIMITED (all its projects)19 (Complaint: 19)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026