RERA’d by NeevHQ

Projects · MARTIAL BUILDCON PVT. LTD.

M3M Urbana Business Park

Martial Buildcon · Sector 67, Gurugram

Registered with RERA: Nov 2017

Is it legal?

Will it be delivered on time?

Location

The builder: Martial Buildcon

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameM3M URBANA BUSINESS PARK
Builder (promoter)MARTIAL BUILDCON PVT. LTD.
LocationSECTOR-67, VILLAGE MAIDAWAS A ND BADSHAHPUR, GURUGRAM, HARYANA
RERA project IDRERA-GRG-603-2020
Registration certificate number347 OF 2017 DATED 09.11.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/11/2021
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area5.025 acres
Licence117 of 2011 dated 23.12.2011
Estimated cost of the project₹36,551.32 lakh (₹365.51 crore)
Total units (plots, apartments, shops)1231
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered932
Units unsold when registered299
Layout plan approved on17-11-2017
Building plans approved on17-11-2017

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-11-2021
Revised completion date30-11-2021
Infrastructure: projected completion30-11-2021
Infrastructure: percentage complete when registered29.88%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusFirst Hearing: 3; Online Complaint Not Yet Received At Office: 1; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against MARTIAL BUILDCON PVT. LTD. (all its projects)48 (Complaint: 41; Compensation: 7)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in