Projects · MARTIAL BUILDCON PVT. LTD.
M3M Urbana Business Park
Martial Buildcon · Sector 67, Gurugram
Registered with RERA: Nov 2017
Is it legal?
- RERA registered, valid till Nov 2021 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not file REP-I (Part A to H) on the web portal for an offline registered project (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2023, open)
- Did not submit a quarterly progress report (May 2022, open)
- 3 more cases: reply 4
- 1 complaint about this project decided by HRERA since Nov 2023 (1 refund ordered)
Will it be delivered on time?
- Deadline Nov 2021, never extended (date has passed)
- 2 occupation certificates issued:
- Sep 2020: Towers A and B, service block and basements (no flats listed)
- Sep 2020: Towers A and B IT and commercial floors, plus basements (no flats listed)
- Quarterly progress report shown as "not uploaded" by HRERA
Location
- Nearest metro: Sector 55–56, 7.2 km by road (24 min by car)
- Cyber City 48 min · Airport 61 min by car at 9:30 am
- Within 3 km: 9 hospitals, 17 schools, 5 malls
The builder: Martial Buildcon
- 2 projects registered in Gurugram
- 2 with an occupation certificate on record
- 48 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | M3M URBANA BUSINESS PARK |
|---|
| Builder (promoter) | MARTIAL BUILDCON PVT. LTD. |
|---|
| Location | SECTOR-67, VILLAGE MAIDAWAS A ND BADSHAHPUR, GURUGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-603-2020 |
|---|
| Registration certificate number | 347 OF 2017 DATED 09.11.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/11/2021 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 5.025 acres |
|---|
| Licence | 117 of 2011 dated 23.12.2011 |
|---|
| Estimated cost of the project | ₹36,551.32 lakh (₹365.51 crore) |
|---|
| Total units (plots, apartments, shops) | 1231 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 932 |
|---|
| Units unsold when registered | 299 |
|---|
| Layout plan approved on | 17-11-2017 |
|---|
| Building plans approved on | 17-11-2017 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-11-2021 |
|---|
| Revised completion date | 30-11-2021 |
|---|
| Infrastructure: projected completion | 30-11-2021 |
|---|
| Infrastructure: percentage complete when registered | 29.88% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|
| Latest report period | Not found in the records checked |
|---|
| Latest report submitted on | Not found in the records checked |
|---|
| Quarterly reports listed on the portal | Not found in the records checked |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR.VII): covers IT Park on 5.025 acres under Licence No. 117 of 2011 dated 23 Dec 2011, Sector-67, Gurugram Manesar Urban Complex. Covers Tower-A (ground to 10th floor, commercial and IT component), Tower-B (ground to 19th floor, commercial and IT component), a service block and basements 1 to 4.. Addressed to Martial Buildcon Private Limited and others. Composition fees for variations from approved plans: ₹11,50,361. Unclear in the document: Date of the memo is garbled and cannot be read, so the issue date is not stated.; Some sanctioned and achieved areas in the building table are garbled or illegible.; Basement-1 area figures are not legible.; Application date is partly garbled; it appears to be 14 Feb 2020.
- Occupation Certificate (Form BR-VII) dated 22 Sep 2020: covers IT Park in Sector-67, Gurugram under Licence No. 117 of 2011. Tower-A (ground floor to 10th floor) and Tower-B (ground floor to 19th floor), each with commercial and IT components. Also a service block and Basements 1 to 4. Land use is commercial and IT component only.. Addressed to Martial Buildcon Pvt. Ltd. & others. Composition fees for variations from approved plans: ₹11,50,381
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | First Hearing: 3; Online Complaint Not Yet Received At Office: 1; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-2620-2022: Non-filing of REP-I (Part A to H) on the Authority's web portal for a project registered offline with the Interim Real Estate Regulatory Authority, Panchkula, or HARERA Gurugram. The Authority issued a notice on this and listed a first hearing. Status: First hearing listed for 29 Jun 2022. The listing shows status 'First Hearing' with no proceedings or order recorded. Latest: 29 Jun 2022, First hearing listed at 11:00 am at HARERA Gurugram. The party may appear to say anything in the matter. The listing shows no proceedings or order uploaded.
- RERA-GRG-3012-2022: The page lists HARERA Gurugram as the party against Martial Buildcon Pvt. Ltd. (the promoter) under complaint RERA-GRG-3012-2022. The page does not state what the proceeding is about. Status: The page shows 'ONLINE COMPLAINT NOT YET RECEIVED AT OFFICE'. Next date of hearing is shown as 'Not Yet'. Complaint dispatch shows 'NA'. The listing of hearings and orders is empty.
- RERA-GRG-3261-2023: The Authority started this suo motu case against the promoter of M3M Urbana Business Park for an alleged violation of Section 4(2)(l)(C) of the RERA Act 2016. The hearings focused on the project's occupation certificate and completion certificate. Status: Pending. The last recorded hearing was on 16 Aug 2023 and the status shown on the case page is PENDING. Latest: 16 Aug 2023, Second hearing. The promoter's authorised representatives attended. They stated the occupation certificate was received on 22 Sep 2020. The Authority directed that the matter be put on file.
- RERA-GRG-3512-2022: Show cause notice to the promoter for not submitting a quarterly progress report Status: Listed for first hearing on 27 Jun 2022. The listing shows status FIRST HEARING, with no proceedings or order recorded. Latest: 27 Jun 2022, First hearing scheduled at 11.00 am at the HARERA office, Gurugram. The promoter was asked to appear and, if it had anything to say, to bring a written reply.
- RERA-GRG-5102-2022: Complaint numbered RERA-GRG-5102-2022, listed in the name of HARERA Gurugram through a representative against Martial Buildcon Pvt. Ltd. The page does not state the subject matter of the complaint. Status: First hearing listed for 30 Jun 2022. The case page shows status FIRST HEARING, no proceedings or order recorded, and no later hearing date. Latest: 16 Jul 2022, A document was received under Dak ID 37981 and recorded as submitted by the complainant's side, with the remark 'NEW COMPLAINT'.
- RERA-GRG-5294-2019: Authority-initiated case against the promoter, Martial Buildcon Pvt. Ltd., for not filing the project's quarterly progress reports (REP-I Part A to H) online, as required under section 11(1) of the Act and the Authority's regulations. Status: Pending. The next hearing was listed for 24 Feb 2020. The case page also shows a fourth notice under section 42lD dispatched on 20 Jul 2020. No hearing outcome is recorded. Latest: 20 Jul 2020, Fourth notice under section 42lD dispatched (dispatch ID EH770719433IN). Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues, cumulatively up to five percent of the estimated cost of the real estate project, as decided by the Authority in its order of 22 Jan 2020.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|
| Cases | |
|---|
| Decided cases against MARTIAL BUILDCON PVT. LTD. (all its projects) | 48 (Complaint: 41; Compensation: 7) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in