Maceo

Anant Raj · Sector 91, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Anant Raj

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameMACEO
Builder (promoter)ANANT RAJ LTD.
LocationSECTOR-91, MANESAR, GURUGRAM
RERA project IDRERA-GRG-363-2019
Registration certificate number63 OF 2017 DATED 18.8.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to17/08/2020
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area15.575 acres
Licence71 of 2008 dated 25.03.2008
Estimated cost of the project₹41,350 lakh (₹413.5 crore)
Total units (plots, apartments, shops)788
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 794–800 sq ft carpet, 275 units; 3 BHK: 1,085–1,949 sq ft carpet, 408 units; 4 BHK: 1,606–2,345 sq ft carpet, 105 units (source: the builder's registration form (Form A-H))
Units booked when registered556
Units unsold when registered232
Layout plan approved on19-09-2017
Building plans approved on18-05-2011

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date16-08-2019
Revised completion date16-08-2020
Infrastructure: projected completion31-03-2020
Infrastructure: percentage complete when registered95%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 2; First Hearing: 3; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against ANANT RAJ LTD. (all its projects)37 (Complaint: 33; Execution of an earlier order: 2; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in