RERA’d by NeevHQ

Projects · GALAXY MONNET INFRAHEIGHTS LTD

Magnum Towers ( Tower A & C)

Galaxy Monnet Infraheights · Sector 58, Gurugram

Registered with RERA: Sep 2017

Is it legal?

Will it be delivered on time?

Location

The builder: Galaxy Monnet Infraheights

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameMAGNUM TOWERS ( TOWER A & C)
Builder (promoter)GALAXY MONNET INFRAHEIGHTS LTD
LocationSECTOR-58, BEHRAMPUR, GURUGRA M
RERA project IDRERA-GRG-631-2020
Registration certificate number225 OF 2017 DATED 19.09.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2018
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.84 acres
Licence82 of 2010 dated 12/10/2010
Estimated cost of the project₹18,240.47 lakh (₹182.4 crore)
Total units (plots, apartments, shops)179
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered159
Units unsold when registered20
Layout plan approved on19-04-2018
Building plans approved on19-04-2018

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-01-2019
Revised completion date30-01-2019
Infrastructure: projected completion30-01-2019
Infrastructure: percentage complete when registered100%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 3; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against GALAXY MONNET INFRAHEIGHTS LTD (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026