Projects · CZAR BUILDWELL PVT. LTD.
Mahira Homes 95
Czar Buildwell · Vill. Dhorka, Sub- Tehsil Kad Ipur, Gurugram
Registered with RERA: Oct 2020
Is it legal?
- Listed by HRERA under "Defaulter / Cancelled / Suspended" projects (the list does not say which of the three)
- HRERA has not opened any case of its own against this project
- 11 complaints about this project decided by HRERA since Nov 2023 (9 refund ordered, 2 other orders)
Will it be delivered on time?
- No occupation certificate yet (not ready for possession)
Location
- Nearest metro: Millennium City Centre Gurugram, 10.1 km by road (38 min by car)
- Cyber City 44 min · Airport 42 min by car at 9:30 am
- Within 3 km: 47 hospitals, 9 schools, 1 mall
The builder: Czar Buildwell
- 3 projects registered in Gurugram, 3 on the defaulter list
- 0 with an occupation certificate on record
- 62 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MAHIRA HOMES 95 |
|---|---|
| Builder (promoter) | CZAR BUILDWELL PVT. LTD. |
| Location | VILL. DHORKA, SUB- TEHSIL KAD IPUR |
| RERA project ID | RERA-GRG-749-2020 |
| Registration certificate number | GGM/416/148/2020/32 DATED 08.10.2020 |
| Registration status | Listed on HRERA Gurugram's "Defaulter / Cancelled / Suspended / Abeyance Projects" page |
| Registration valid up to | Not found in the records checked |
| Registered with | Not found in the records checked |
| Registration certificate | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Not found in the records checked |
|---|
Source: not checked yet
Project details (from the registration form, Form A-H)
| Project type | Not found in the records checked |
|---|---|
| Land area | Not found in the records checked |
| Licence | Not found in the records checked |
| Estimated cost of the project | Not found in the records checked |
| Total units (plots, apartments, shops) | Not found in the records checked |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | Not found in the records checked |
| Building plans approved on | Not found in the records checked |
Source: not checked yet
Timeline declared by the builder
| Likely start of construction | Not found in the records checked |
|---|---|
| Likely completion date | Not found in the records checked |
Source: not checked yet
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in