Projects · MAPSKO BUILDERS PVT. LTD.
Mapsko Mount Ville
Mapsko Builders · Sector 78 & 79, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till Aug 2020 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report (QPR), prompting show-cause notice (May 2022, open)
- Did not submit completion, part completion or occupation certificate after extension lapsed; absent from several hearings (Jun 2022, open)
- Repeated notices to comply with Section 42(1)(D) REP-I filing and quarterly progress report (Nov 2019, open)
- 3 more cases: reply 4
Will it be delivered on time?
- Deadline Aug 2020, never extended (date has passed)
- Occupation certificate (Jun 2020) covers: Clusters 1A-1F, 2, 3, EWS block, shops and community building (756 flats)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 3 BHK: 862–867 sq ft carpet, 604 units
- 3 BHK + servant room: 1,071–1,074 sq ft carpet, 110 units
- 4 BHK + servant room: 1,688 sq ft carpet, 42 units
Location
- Nearest metro: Millennium City Centre Gurugram, 20.8 km by road (53 min by car)
- Cyber City 59 min · Airport 50 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Mapsko Builders
- 3 projects registered in Gurugram
- 1 with an occupation certificate on record
- 101 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MAPSKO MOUNT VILLE |
|---|---|
| Builder (promoter) | MAPSKO BUILDERS PVT. LTD. |
| Location | SECTOR-78 & 79, GURUGRAM, HAR YANA |
| RERA project ID | RERA-GRG-365-2019 |
| Registration certificate number | 328 OF 2017 DATED 23.10.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/08/2020 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 15.527 acres |
| Licence | 38 OF 2012 |
| Estimated cost of the project | ₹52,500 lakh (₹525 crore) |
| Total units (plots, apartments, shops) | 756 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 3 BHK: 862–867 sq ft carpet, 604 units; 3 BHK + servant room: 1,071–1,074 sq ft carpet, 110 units; 4 BHK + servant room: 1,688 sq ft carpet, 42 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 409 |
| Units unsold when registered | 347 |
| Layout plan approved on | 01-05-2013 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-11-2019 |
|---|---|
| Revised completion date | 30-08-2020 |
| Infrastructure: projected completion | 30-08-2020 |
| Infrastructure: percentage complete when registered | 90% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against MAPSKO BUILDERS PVT. LTD. (all its projects) | 101 (Complaint: 87; Compensation: 12; Execution of an earlier order: 2) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in