Projects · EMAAR INDIA LIMITED
Marbella Phase 7
Emaar India · Sector 66, Gurugram
Registered with RERA: Aug 2026
Is it legal?
- RERA registered, valid till Dec 2026
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Dec 2031, never extended
- No occupation certificate yet (not ready for possession)
What's on offer?
- 12 plots, 358–500 sq yd
Location
- Nearest metro: Sector 55–56, 6.1 km by road (22 min by car)
- Cyber City 47 min · Airport 53 min by car at 9:30 am
- Within 3 km: 14 hospitals, 20 schools, 8 malls
The builder: Emaar India
- 20 projects registered in Gurugram, 2 lapsed
- 0 with an occupation certificate on record
- 97 buyer complaints decided by HRERA
★ Emaar India was earlier called Emaar MGF Land Ltd. Its history under the earlier name matters too: 22 projects (19 with an occupation certificate), 1,022 decided buyer complaints.
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MARBELLA PHASE 7 |
|---|---|
| Builder (promoter) | EMAAR INDIA LIMITED |
| Location | SECTOR 66 |
| RERA project ID | RERA-GRG-2230-2026 |
| Registration certificate number | RC/REP/YHARERA/GGM/1080/812/2026/52 DATED 05.08.2026 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 2.594 acres |
| Licence | . 97 of 2010 dated 18.11.2010, License No. 41 of 2011 dated 03.05.2011, License No. 101 of 2023 dated 06.05.2023, License No. 265 of 2025 dated 31.12.2025. |
| Estimated cost of the project | ₹1,725.03 lakh (₹17.25 crore) |
| Total units (plots, apartments, shops) | 12 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 26-05-2026 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-07-2026 |
|---|---|
| Likely completion date | 31-12-2031 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | NA |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against EMAAR INDIA LIMITED (all its projects) | 97 (Execution of an earlier order: 36; Complaint: 57; Compensation: 4) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in