Projects · EMAAR INDIA LIMITED

Marbella Terraces

Emaar India · Sector 66, Gurugram

Registered with RERA: Jun 2026

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 66; the exact site was not found.

The builder: Emaar India

★ Emaar India was earlier called Emaar MGF Land Ltd. Its history under the earlier name matters too: 22 projects (19 with an occupation certificate), 1,022 decided buyer complaints.

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameMARBELLA TERRACES
Builder (promoter)EMAAR INDIA LIMITED
LocationSECTOR 66
RERA project IDRERA-GRG-2228-2026
Registration certificate numberGM/1068/800/2026/40 DATED 25.06.2026
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2031
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area20.24225 acres
Licence97 of 2010 dt 18.11.2010, 41 of 2011 dt. 03.05.2011, 101 of 2023 dt. 06.05.2023, 265 of 2025dt. 31.12.2025
Estimated cost of the project₹83,344.79 lakh (₹833.45 crore)
Total units (plots, apartments, shops)247
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on26-05-2026
Building plans approved on26-05-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2026
Likely completion date31-12-2031

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal1

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹500 lakh (₹5 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,192 lakh (₹11.92 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹4,336 lakh (₹43.36 crore)
Project bank account (escrow): deposited in the quarter₹350 lakh (₹3.5 crore)
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹350 lakh (₹3.5 crore)
Units in the project (apartments / plots)247 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹13,281.31 lakh (₹132.81 crore) paid; ₹518.95 lakh (₹5.19 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 21-08-2026
  • Demarcation Plan: Obtained Approval 24-09-2026
  • Zoning Plan: Obtained Approval 23-06-2026
  • Service Plans: Obtained Approval 25-06-2026
  • Electricity Plans: Obtained Approval 23-06-2026

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Oct 2026, for Sept 26
By part
  • Plots: not stated
  • Internal roads & pavements: 0%
  • Parking (open): 0%
  • Water supply: 0%
  • Sewerage (chamber, lines, septic tanks, STP): 0%
  • Storm water drains: 0%
  • Landscaping & tree plantation: 0%
  • Benches: 0%
  • Street lighting/ electrification: 0%
  • Treatment and disposal of sewage and sullage water/STP: 0%
  • Water conservation, rainwater harvesting, percolating well/pit: 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
Unclear in the certificate
  • Table A shows only dashes or NA for all work items under Plots, so no percentage is given for it

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against EMAAR INDIA LIMITED (all its projects)97 (Execution of an earlier order: 36; Complaint: 57; Compensation: 4)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026