Projects · SILVERLAKE BUILDTECH PVT.LTD.
Maruti Kunj
Silverlake Buildtech · Tehsil Farrukhnagar, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Aug 2022 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not file REP-I (Part A to H) on the web portal for an offline registered project (Jun 2022, open)
- Did not submit quarterly progress report, prompting show-cause notice (May 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2023, open). At stake: Authority warned of bank account freezing and sale restrictions if non-compliant; no amount stated
- 3 more cases: reply 4
Will it be delivered on time?
- Deadline Aug 2022, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- 24 units in 18 sizes, as declared to HRERA:
- 1 unit of 748 sq ft carpet
- 1 unit of 776 sq ft carpet
- 1 unit of 873 sq ft carpet
- 3 units of 1,225 sq ft carpet
- 3 units of 1,491 sq ft carpet
- 2 units of 1,606 sq ft carpet
- 12 less common sizes: see the full list below
- 1 unit: the size the builder entered is not possible, so it is not shown
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
- 245 plots, 97–178 sq yd
The builder: Silverlake Buildtech
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Full details and sources are below.
Registration
| Project name | MARUTI KUNJ |
|---|---|
| Builder (promoter) | SILVERLAKE BUILDTECH PVT.LTD. |
| Location | TEHSIL FARRUKHNAGAR,GURUGRAM |
| RERA project ID | RERA-GRG-661-2020 |
| Registration certificate number | 127 OF 2017 DATED 28.08.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 27/08/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 12.85625 acres |
| Licence | 18 of 2017 dated 15.05.2017 |
| Estimated cost of the project | ₹2,682.81 lakh (₹26.83 crore) |
| Total units (plots, apartments, shops) | 269 |
| Unit sizes (carpet area, as declared) | 1 unit of 748 sq ft carpet; 1 unit of 776 sq ft carpet; 1 unit of 873 sq ft carpet; 1 unit of 1,057 sq ft carpet; 3 units of 1,225 sq ft carpet; 1 unit of 1,242 sq ft carpet; 1 unit of 1,351 sq ft carpet; 1 unit of 1,433 sq ft carpet; 3 units of 1,491 sq ft carpet; 1 unit of 1,525 sq ft carpet; 1 unit of 1,537 sq ft carpet; 1 unit of 1,558 sq ft carpet; 1 unit of 1,568 sq ft carpet; 1 unit of 1,577 sq ft carpet; 1 unit of 1,587 sq ft carpet; 1 unit of 1,597 sq ft carpet; 2 units of 1,606 sq ft carpet; 1 unit of 1,616 sq ft carpet |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 30-10-2017 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 30-09-2017 |
|---|---|
| Likely completion date | 27-08-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SILVERLAKE BUILDTECH PVT.LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in