Projects · SILVERGLADES INFRASTRUCTURE PVT. LTD.
Merchant Plaza
Silverglades Infrastructure · Sector 88, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till Dec 2020 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit the quarterly progress report; Authority issued a show-cause notice on 31 May 2022 (May 2022, open)
- Did not apply for registration extension or submit completion, occupation certificate and documents (Jun 2022, open)
- Allegedly did not complete Merchant Plaza project within its declared completion time (Jun 2022, open)
- 3 more cases: reply 4
- 12 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 5 refund ordered, 6 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Dec 2020, never extended (date has passed)
- Occupation certificate (Feb 2020) covers: Commercial block, Sector-88 Gurugram, ground to 11th floor (no flats listed)
- Construction, as certified by the architect (Oct–Dec 2024):
- Done: Merchant plaza - sub structure, Merchant plaza - super structure
- In progress: Merchant plaza - finishing external 98%, Merchant plaza - external development works 96%, Merchant plaza - finishing internal 93%, Merchant plaza - mep plumbing and firefighting 92%, Merchant plaza - mep mechanical 87%, Merchant plaza - mep electrical 47%
- Money: ₹200.6 crore spent of ₹209.4 crore; ₹8.8 crore still to spend (CA certificate, Dec 2024)
Location
- Nearest metro: Millennium City Centre Gurugram, 17.8 km by road (48 min by car)
- Cyber City 54 min · Airport 38 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Silverglades Infrastructure
- 2 projects registered in Gurugram, 1 lapsed
- 1 with an occupation certificate on record
- 54 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MERCHANT PLAZA |
|---|
| Builder (promoter) | SILVERGLADES INFRASTRUCTURE PVT. LTD. |
|---|
| Location | SECTOR-88, VILLAGE HAYATPUR, GURUGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-507-2019 |
|---|
| Registration certificate number | 340 OF 2017 DATED 27.10.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 20/12/2020 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 2.75625 acres |
|---|
| Licence | 1 of 2013 |
|---|
| Estimated cost of the project | ₹19,643 lakh (₹196.43 crore) |
|---|
| Total units (plots, apartments, shops) | 415 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 0 |
|---|
| Units unsold when registered | 0 |
|---|
| Layout plan approved on | 01-11-2014 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 20-12-2020 |
|---|
| Revised completion date | 20-12-2020 |
|---|
| Infrastructure: projected completion | 20-12-2020 |
|---|
| Infrastructure: percentage complete when registered | 100% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/12/2024 (OCT-DEC) |
|---|
| Latest report submitted on | 07-Feb-2025 |
|---|
| Quarterly reports listed on the portal | 25 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2024 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹54.9 lakh (₹0.55 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | Not found in the records checked |
|---|
| Sold in the quarter | Not found in the records checked |
|---|
| EDC (development charges): paid / due as on date | ₹1,376.27 lakh (₹13.76 crore) paid; ₹220.51 lakh (₹2.21 crore) due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 30-05-2013
- Zoning Plan: Obtained Approval 30-05-2013
- Service Plans: Obtained Approval 07-12-2017
- Electricity Plans: Obtained Approval 07-12-2017
- Site Plans: Obtained Approval 30-05-2013
- Building Plans: Obtained Approval 30-05-2013
- Fire NOC: Obtained Approval 28-08-2019
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | for Dec - 2024 |
|---|
| By part | - Merchant Plaza - Sub structure: 100%
- Merchant Plaza - Super structure: 100%
- Merchant Plaza - MEP Mechanical (lifts, ventilation): 87%
- Merchant Plaza - MEP Electrical (conducting, wiring, fixtures): 47%
- Merchant Plaza - MEP Plumbing and Firefighting (piping, pumps, fixtures): 92%
- Merchant Plaza - Finishing Internal (plaster, tiling, flooring, painting): 93%
- Merchant Plaza - Finishing External (plaster, painting, facade): 98%
- Merchant Plaza - External development works: 96%
|
|---|
| Unclear in the certificate | - The date of certifying the percentage of work and the date of site inspection are blank in the certificate.
- The certificate's signing date and place are blank.
- Table B (activity-wise status) gives further percentages that are not listed here.
- The certificate shows work value of 0 for the quarter for every Table A item.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 3; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-3009-2022: Complaint RERA-GRG-3009-2022, listed as HARERA Gurugram (through a named representative) against Silverglades Infrastructure Pvt. Ltd. The page does not state what the complaint is about. Status: Online complaint not yet received at office. Complaint dispatch shows 'Not Yet' and tracking ID is NA.
- RERA-GRG-3509-2022: Show cause notice to the promoter for not submitting the quarterly progress report. The Authority asked the promoter to explain in writing and attend a first hearing. Status: First hearing scheduled for 27 Jun 2022. The case page lists the status as FIRST HEARING, with no proceedings of the day or order recorded. Latest: 27 Jun 2022, First hearing listed in the Authority's records for this case.
- RERA-GRG-3783-2022: The Authority issued a show cause notice to the promoter, Silverglades Infrastructure Pvt. Ltd., for not applying for extension of registration and for not submitting the completion, part completion or occupation certificate, and for not submitting the requisite documents. Status: First hearing listed for 28 Jun 2022. The page records no proceedings or order for that hearing. Latest: 28 Jun 2022, First hearing was listed. Proceedings, bench and order fields are blank or marked '---'.
- RERA-GRG-3784-2022: Suo motu proceeding by the Authority against Silverglades Infrastructure Pvt. Ltd. for allegedly not completing the Merchant Plaza project within the time it declared, under section 4(2)(l)(C) of the RERA Act, 2016. Status: Pending. The next hearing was fixed for 20 Sep 2024. At that hearing the promoter's representative said an occupation certificate dated 11 Feb 2020 was received within the registration validity and possession had been offered to allottees. The Authority directed that the status of the occupation certificate with respect to the registered area be examined and the matter be put up on file. Latest: 20 Sep 2024, Promoter's representative appeared. Said occupation certificate was received within registration validity and possession was offered to allottees. Authority directed examination of the occupation certificate status against the registered area and the matter to be put on file.
- RERA-GRG-5108-2022: A case listed as HARERA Gurugram versus Silverglades Infrastructure Pvt. Ltd. The page does not state the reason for the case. Status: First hearing listed for 30 Jun 2022. The page shows no order uploaded for that hearing. Latest: 16 Jul 2022, A document was received and recorded as a new complaint submission by the complainant's side.
- RERA-GRG-5477-2019: The Authority's own proceeding against the promoter, Silverglades Infrastructure Pvt. Ltd., for not submitting project updates (REP-I Part A-H) on the web page as required under section 11(1) of the Act and rule 14(1)(d) of the Rules. Status: Pending. The Authority directed the promoter to submit REP-I (Part A-H) online and in hard copy, and issued a show cause notice. The next personal hearing is listed for 24 Feb 2020 at 3:00 pm. A third notice was dispatched on 20 Jul 2020. Latest: 20 Jul 2020, Third notice was dispatched to the promoter. Penalty: The Authority decided to impose a penalty of Rs 25,000 per day from 31 Dec 2019 while the default continues. The total may extend up to five percent of the estimated cost of the real estate project, as determined by the Authority.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 12 |
|---|
| Cases | - RERA-GRG-6425-2024 (compensation, decided 10-Sep-2026): Buyer sought compensation for alleged violations; HRERA dismissed the complaint finding no violation proved.
- RERA-GRG-30-2023 (compensation, decided 30-Oct-2025): Buyer sought compensation for delayed shop possession; authority dismissed it because interest for the delay was already awarded earlier.
- RERA-GRG-753-2023 (compensation, decided 30-Oct-2025): Buyer sought compensation for delayed shop possession; complaint dismissed because delay interest was already awarded earlier.
- RERA-GRG-758-2023 (compensation, decided 30-Oct-2025): Buyer sought compensation for delayed flat possession; complaint dismissed as interest was already allowed earlier.
- RERA-GRG-15-2023 (compensation, decided 30-Oct-2025): Buyer sought Rs 18 lakh compensation for delay and related issues; complaint dismissed as interest was already awarded earlier.
- RERA-GRG-2978-2023 (compensation, decided 30-Oct-2025): Buyer sought compensation for delayed shop possession; authority dismissed claim as delay interest was already awarded.
- RERA-GRG-135-2023 (compensation, decided 30-Oct-2025): Buyer sought compensation for delayed shop possession; builder already ordered to pay interest earlier, so complaint dismissed.
- RERA-GRG-1051-2020 (complaint, decided 14-May-2024): Buyer sought refund of Rs 16.42 lakh after years of unexecuted agreement; builder ordered to refund after 10% deduction with 10.85% interest.
- RERA-GRG-3571-2020 (complaint, decided 27-Feb-2024): Builder sought dues and possession; buyers surrendered allotment. HRERA ordered refund of Rs 73.77 lakh less 10% earnest money, with 10.85% interest.
- RERA-GRG-1701-2022 (complaint, decided 16-Feb-2024): Buyer sought refund after surrendering unit before possession; builder ordered to refund Rs 10.40 lakh with 10.85% interest.
- RERA-GRG-1702-2022 (complaint, decided 16-Feb-2024): Buyer sought refund of payments after a delayed possession; builder ordered to refund Rs 15.33 lakh with 10.85% interest.
- RERA-GRG-3146-2020 (complaint, decided 06-Feb-2024): Buyer sought refund after possession delay; builder ordered to refund Rs 11.6 lakh less 10% earnest money, with 10.85% interest.
|
|---|
| Decided cases against SILVERGLADES INFRASTRUCTURE PVT. LTD. (all its projects) | 54 (Complaint: 31; Compensation: 12; Execution of an earlier order: 11) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in