Projects · MICROTEK URBANDEVELOPERS PVT. LTD.
Microtek Success Hub
Microtek Urbandevelopers · Sector 95, Gurugram
Registered with RERA: May 2023
Is it legal?
- RERA registered, valid till Jul 2025 (date has passed)
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Jul 2025, never extended (date has passed)
- Occupation certificate (Jul 2025) covers: Commercial plotted colony, 4.0 acres, Sector-95A Gurugram (no flats listed)
- Construction, as certified by the architect (Jul–Sep 2025):
- Done: Internal roads & pavements, Water supply, Sewerage, Storm water drains, Electrical meter room, sub-station, receiving station
- Money: ₹75.8 crore spent of ₹96.8 crore; ₹21 crore still to spend (CA certificate, Sep 2025)
What's on offer?
- 53 units: 41 sold, 12 unsold (builder's certificate, Sep 2025)
- Plots: 41 of 53 sold
- 53 plots, 74–144 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 22.9 km by road (58 min by car)
- Cyber City 60 min · Airport 40 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Microtek Urbandevelopers
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MICROTEK SUCCESS HUB |
|---|---|
| Builder (promoter) | MICROTEK URBANDEVELOPERS PVT. LTD. |
| Location | VILLAGE WAZIRPUR SECTOR 95-A GURUGRAM |
| RERA project ID | RERA-GRG-1295-2023 |
| Registration certificate number | GGM/714/446/2023/58 DATED 08.05.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/07/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 4.0 acres |
| Licence | 201 OF 2022 DATED 01.12.2022 ISSUED BY DGTCP HARYANA AT CHANDIGARH |
| Estimated cost of the project | ₹7,382.15 lakh (₹73.82 crore) |
| Total units (plots, apartments, shops) | 53 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 05-12-2022 |
| Building plans approved on | 20-04-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-02-2023 |
|---|---|
| Likely completion date | 31-07-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2025 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2025 |
| Quarterly reports listed on the portal | 9 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2025 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,346.94 lakh (₹13.47 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹-1,145.52 lakh (₹-11.46 crore) |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹81.06 lakh (₹0.81 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹174.64 lakh (₹1.75 crore) |
| Project bank account (escrow): deposited in the quarter | ₹942.86 lakh (₹9.43 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹847.48 lakh (₹8.47 crore) |
| Project bank account (escrow): balance at quarter end | ₹135.72 lakh (₹1.36 crore) |
| Units in the project (apartments / plots) | 53 plots |
| Sold in the quarter | 4 plots |
| EDC (development charges): paid / due as on date | ₹1,665.6 lakh (₹16.66 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 03 Oct 2025, for 30 Sep 2025 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against MICROTEK URBANDEVELOPERS PVT. LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in