Projects · IMPERIA STRUCTURES LTD.
Mindspace
Imperia Structures · Sector 62, Gurugram
Registered with RERA: Sep 2017
Is it legal?
- RERA registered, valid till Dec 2020 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit a quarterly progress report, prompting a show-cause notice (May 2022, open)
- Did not apply to extend expired registration or submit completion, part completion or occupation certificate (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
- 14 complaints about this project decided by HRERA since Nov 2023 (3 delay interest ordered, 3 refund ordered, 5 assured return ordered, 3 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Dec 2020, never extended (date has passed)
- Occupation certificate (Jun 2020) covers: Tower-C and basements only (no flats listed)
- Money: ₹205.2 crore spent of ₹217.5 crore; ₹12.3 crore still to spend (CA certificate, Jun 2025)
What's on offer?
- 287 units: 282 sold, 5 unsold (builder's certificate, Dec 2025)
- RETAIL: 23 of 23 sold
- VIRTUAL: 259 of 264 sold
Location
- Nearest metro: Sector 55–56, 4.4 km by road (16 min by car)
- Cyber City 42 min · Airport 59 min by car at 9:30 am
- Within 3 km: 5 hospitals, 13 schools, 5 malls
The builder: Imperia Structures
- 2 projects registered in Gurugram
- 2 with an occupation certificate on record
- 141 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MINDSPACE |
|---|
| Builder (promoter) | IMPERIA STRUCTURES LTD. |
|---|
| Location | SECTOR-62, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-358-2019 |
|---|
| Registration certificate number | 240 OF 2017 DATED 25.09.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 31/12/2020 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 2.104 acres |
|---|
| Licence | 86 of 2010 dated 23.10.2010 |
|---|
| Estimated cost of the project | ₹9,006.66 lakh (₹90.07 crore) |
|---|
| Total units (plots, apartments, shops) | 0 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 0 |
|---|
| Units unsold when registered | 0 |
|---|
| Layout plan approved on | 22-08-2019 |
|---|
| Building plans approved on | 22-08-2019 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-12-2020 |
|---|
| Revised completion date | 31-12-2020 |
|---|
| Infrastructure: projected completion | 30-09-2020 |
|---|
| Infrastructure: percentage complete when registered | 56.14% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/06/2025 (APR-JUN) |
|---|
| Latest report submitted on | 02-Feb-2026 |
|---|
| Quarterly reports listed on the portal | 27 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2025 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹225.47 lakh (₹2.25 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹2.11 lakh (₹0.02 crore) |
|---|
| Spent on infrastructure in the quarter | ₹53.86 lakh (₹0.54 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹1.73 lakh (₹0.02 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 287 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹927.12 lakh (₹9.27 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 04-12-2015
- Demarcation Plan: Obtained Approval 16-03-2013
- Zoning Plan: Obtained Approval 16-03-2013
- Service Plans: Obtained Approval 07-11-2019
- Electricity Plans: Obtained Approval 15-11-2019
- Site Plans: Obtained Approval 04-12-2015
- Building Plans: Obtained Approval 04-12-2015
- Fire NOC: Obtained Approval 06-12-2019
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 04 Jul 2025, for 01 Apr 2025 to 30 Jun 2025 |
|---|
| By part | - Mindspace tower (Table A, Baakir Phase-II): Sub-structure 100% complete. Super-structure 100% structure complete (G+13 floors). Walls on floors 98%. Internal wall finishing 95%. Units/flats flooring 95%. Sanitary fixtures 0%. Waterproofing of terraces 0%. Entrance lobby finishing 0%. Compound wall 100%.
|
|---|
| Unclear in the certificate | - The certificate gives no single overall percentage for the tower; progress is listed by activity only.
- The architect's Council of Architects registration number and registration validity date are blank.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR-VII) dated 02 Jun 2020: covers Tower-C (ground floor to 13th floor, including commercial space at ground floor) and the basements, as stated in condition 18. The building is in the IT/Cyber Park Colony, Sector-62, Gurugram (Licence No. 86 of 2010, total area 8.356 acres). The approved plan table also lists non-FAR areas: ground floor BUA, MLCP from 1st to 4th floor, Basement-I and II, mumty and machine room, and staircase, refuge and AHU.. Addressed to Baakir Real Estate Pvt. Ltd.. Composition fees for variations from approved plans: ₹3,53,862. Unclear in the document: The endorsement memo number and date are blank on the copy provided.; The document does not state a number of dwelling units; it refers only to IT/commercial spaces.
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2899-2022: A complaint filed by the complainant against Imperia Structures Ltd, numbered RERA-GRG-2899-2022. The page is titled HARERA Gurugram, with the complainant listed as 'Self' and the district as Gurugram. It shows no reason for the complaint. Status: The page shows 'Online complaint not yet received at office'. Dispatch status is 'Not Yet'. No next hearing date is listed (NA). The complaint listing table has no entries.
- RERA-GRG-3357-2022: Show cause notice issued by the Authority against the promoter for not submitting a quarterly progress report Status: First hearing listed for 27 Jun 2022 before the Authority at Gurugram; the page shows the status as FIRST HEARING with no order uploaded. Latest: 27 Jun 2022, First hearing listed at 11.00 am at the HARERA office, Gurugram, where the promoter was asked to appear with a written reply if it had anything to say. Listing shows status FIRST HEARING, with no proceedings or order recorded.
- RERA-GRG-3364-2022: Show cause notice to the promoter for not applying to extend its registration, which has expired, and for not submitting a completion, part completion or occupation certificate and the required documents. The Authority started this case itself. Status: First hearing listed for 28 Jun 2022. The case page shows the status as 'First Hearing' with no proceedings recorded and no order uploaded. Latest: 28 Jun 2022, First hearing was listed. The page records no proceedings, bench order or uploaded order for this date.
- RERA-GRG-3367-2022: The Authority issued a show-cause notice to the promoter, Imperia Structures Ltd, for not completing the project within the time it declared, under section 4(2)(l)(C) of the RERA Act. Status: First hearing listed for 30 Jun 2022. The listing shows the status as FIRST HEARING, with no proceedings or order recorded and no order uploaded. Latest: 30 Jun 2022, First hearing was listed. No proceedings of the day or bench order are recorded.
- RERA-GRG-5184-2022: A complaint numbered RERA-GRG-5184-2022 listed against Imperia Structures Ltd, the promoter. The page lists the complainant as HARERA Gurugram through an individual. The page does not state the reason for the complaint. Status: First hearing listed for 30 Jun 2022. The page shows no proceedings or order for that hearing. Latest: 16 Jul 2022, A document titled 'New Complaint' was received under a Dak ID and recorded as submitted by the complainant.
- RERA-GRG-5396-2019: The Authority's case against promoter Imperia Structures Ltd for failing to submit REP-I (Part A-H) project updates on the web portal and quarterly progress reports for the Mindspace project, Sector 62, Gurugram. Status: Pending. The case page shows the next hearing on 24 Feb 2020. A fifth notice was dispatched on 20 Jul 2020. Latest: 20 Jul 2020, Fifth notice was dispatched, and the complaint was dispatched. Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues. The penalty may cumulatively extend up to five percent of the estimated cost of the real estate project, as determined by the Authority. This was decided on 22 Jan 2020.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 14 |
|---|
| Cases | - RERA-GRG-6069-2025 (complaint, decided 18-Sep-2026): Buyer's unit cancelled over unpaid dues; HRERA upheld cancellation, ordered builder to refund Rs 13.5 lakh with 10.80% interest.
- RERA-GRG-254-2024 (compensation, decided 07-Sep-2026): Buyer sought compensation for delayed possession; complaint dismissed as delay compensation was already allowed earlier.
- RERA-GRG-6226-2024 (complaint, decided 07-Apr-2026): Buyer sought reinstatement of cancelled unit; authority ordered arrears of assured return, conveyance deed after occupancy certificate.
- RERA-GRG-1532-2023 (complaint, decided 07-Apr-2026): Buyer sought reinstatement of cancelled unit; authority ordered arrears of assured return, conveyance deed after occupancy certificate.
- RERA-GRG-5829-2024 (complaint, decided 07-Apr-2026): Buyer sought delayed-possession relief and conveyance deed; HRERA ordered conveyance deed within one month of occupancy certificate.
- RERA-GRG-2638-2025 (complaint, decided 12-Mar-2026): Buyer sought refund with interest for delayed possession; complaint dismissed as not maintainable due to earlier settlement.
- RERA-GRG-6408-2024 (complaint, decided 23-Dec-2025): Buyers sought refund after unit cancellation; builder ordered to refund Rs 24.24 lakh minus 10% earnest money, with 10.80% interest.
- RERA-GRG-6409-2024 (complaint, decided 23-Dec-2025): Buyers were refunded after builder cancelled unit for non-payment; builder ordered to refund Rs 39 lakh less 10% with 10.80% interest.
- RERA-GRG-5842-2024 (complaint, decided 12-Dec-2025): Buyer of virtual office space in Mindspace, Gurugram sought possession and delay interest; builder ordered to pay 10.85% interest, no physical possession.
- RERA-GRG-1875-2025 (complaint, decided 09-Dec-2025): Allottee sought conveyance deed and no holding charges; HRERA dismissed complaint as time-barred but ordered conveyance deed within 30 days and no holding charges.
- RERA-GRG-3812-2024 (complaint, decided 01-Aug-2025): Buyer sought possession and delay charges; HRERA declined delay charges as assured returns were paid, and ordered possession within 30 days.
- RERA-GRG-3585-2023 (complaint, decided 01-Aug-2025): Buyers sought possession and delay charges for a virtual office space; builder ordered to pay assured return and rental, not physical possession.
- RERA-GRG-4136-2024 (complaint, decided 30-Jul-2025): Buyer sought committed leasing returns and revocation of holding charges; HRERA ordered builder to pay assured and committed returns, barred holding charges.
- RERA-GRG-3186-2023 (complaint, decided 16-Jul-2025): Buyer sought unpaid lease rent after builder failed to lease unit; HRERA ordered builder to pay committed rent of Rs 29,077 monthly and lease the unit.
|
|---|
| Decided cases against IMPERIA STRUCTURES LTD. (all its projects) | 141 (Complaint: 123; Compensation: 5; Execution of an earlier order: 13) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in