Projects · MANGLAM MULTIPLEX PRIVATE LIMITED
Mixed Land Use (Residential (M3M Heights, M3M Skycity) & Commercial (M3M 65TH Avenue))
Manglam Multiplex · Sector 65, Gurugram
Registered with RERA: Feb 2023
Is it legal?
- RERA registered, valid till May 2025 (date has passed)
- HRERA opened a case of its own against the builder in Aug 2025 (still open):
- Why: did not complete M3M Heights, Skycity and 65th Avenue projects within declared time
- Latest: next hearing scheduled 01 Oct 2025; builder must file completion status and CC/OC
- 16 complaints about this project decided by HRERA since Nov 2023 (2 delay interest ordered, 7 refund ordered, 3 assured return ordered, 2 compensation ordered, 1 other order, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline May 2024, extended to May 2025
- The order keeps buyers' right to a refund or interest for the delay
- 3 occupation certificates issued:
- Sep 2021: Retail Blocks 1 to 8 and Multiplex, Sector-65 Gurugram (no flats listed)
- Oct 2023: Towers 1A, 1B, 6A, 6B, EWS block, retail and school (744 flats)
- Sep 2024: Towers 2, 3, 4 and 5 in mixed-use TOD colony (720 flats)
- Construction, as certified by the architect (Jan–Mar 2025):
- Done: 8 parts
- Money: ₹2,115.8 crore spent of ₹2,259.8 crore; ₹144 crore still to spend (CA certificate, Mar 2025)
What's on offer?
- 2,369 units: 2,347 sold, 22 unsold (builder's certificate, Mar 2025)
- Registration now covers 2359
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
- 3 BHK
- 3 BHK + servant room
Location
- Nearest metro: Sector 55–56, 6.1 km by road (22 min by car)
- Cyber City 46 min · Airport 56 min by car at 9:30 am
- Within 3 km: 17 hospitals, 27 schools, 7 malls
The builder: Manglam Multiplex
- 5 projects registered in Gurugram, 1 lapsed
- 3 with an occupation certificate on record
- 61 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MIXED LAND USE (RESIDENTIAL (M3M HEIGHTS, M3M SKYCITY) & COMMERCIAL (M3M 65TH AVENUE)) |
|---|---|
| Builder (promoter) | MANGLAM MULTIPLEX PRIVATE LIMITED |
| Location | SECTOR 65, GURUGRAM |
| RERA project ID | RERA-GRG-1284-2023 |
| Registration certificate number | GGM/688/420/2023/32 DATED 02.02.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 01/05/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 14.4125 acres |
| Licence | 15 of 2017 dated 02.05.2017 |
| Estimated cost of the project | ₹2,25,977.2 lakh (₹2,259.77 crore) |
| Total units (plots, apartments, shops) | 2369 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK; 3 BHK; 3 BHK + servant room (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | 2182 |
| Units unsold when registered | 187 |
| Layout plan approved on | 16-12-2022 |
| Building plans approved on | 16-12-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 01-05-2024 |
|---|---|
| Revised completion date | 01-05-2024 |
| Infrastructure: projected completion | 30-11-2023 |
| Infrastructure: percentage complete when registered | 60% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2025 (JAN-MAR) |
| Latest report submitted on | 15-Apr-2025 |
| Quarterly reports listed on the portal | 8 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹2,260.83 lakh (₹22.61 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,554.85 lakh (₹15.55 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹343.78 lakh (₹3.44 crore) |
| Project bank account (escrow): deposited in the quarter | ₹2,260.83 lakh (₹22.61 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹2,260.79 lakh (₹22.61 crore) |
| Project bank account (escrow): balance at quarter end | ₹0.04 lakh (₹0 crore) |
| Units in the project (apartments / plots) | 2379 apartments |
| Sold in the quarter | 1 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Mar 2025, for January to March 2025 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in