Projects · METRO TECHNO BUILD PVT. LTD.
Mks Country-Phase I
Metro Techno Build · Sector 2, Gurugram
Registered with RERA: Feb 2019
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till May 2024)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit its quarterly progress report, prompting a show-cause notice from the Authority (open)
- Did not complete project within the time it declared; registration certificate expired (Jul 2025, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Sep 2024, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- 494 units in 20 sizes, as declared to HRERA:
- 130 units of 173 sq ft carpet
- 68 units of 615 sq ft carpet (4 towers)
- 36 units of 719 sq ft carpet (4 towers)
- 34 units of 861 sq ft carpet (3 towers)
- 93 units of 880 sq ft carpet (2 towers)
- 66 units of 1,076 sq ft carpet
- 14 less common sizes: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Sector 55–56, 25.7 km by road (53 min by car)
- Cyber City 68 min · Airport 73 min by car at 9:30 am
- Within 3 km: 3 hospitals, 1 school, 0 malls
The builder: Metro Techno Build
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MKS COUNTRY-PHASE I |
|---|---|
| Builder (promoter) | METRO TECHNO BUILD PVT. LTD. |
| Location | SECTOR-2, SOHNA, GURUGRAM |
| RERA project ID | RERA-GRG-100-2018 |
| Registration certificate number | GGM/315/47/2019/09 DATED 21.02.2019 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 19/05/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 4.66 acres |
| Licence | 162 of 2014(12.09.2014) |
| Estimated cost of the project | ₹21,803 lakh (₹218.03 crore) |
| Total units (plots, apartments, shops) | 494 |
| Unit sizes (carpet area, as declared) | 2 units of 78 sq ft carpet (6 towers); 2 units of 172 sq ft carpet (6 towers); 130 units of 173 sq ft carpet; 7 units of 225 sq ft carpet (6 towers); 2 units of 581 sq ft carpet (4 towers); 68 units of 615 sq ft carpet (4 towers); 2 units of 700 sq ft carpet (4 towers); 36 units of 719 sq ft carpet (4 towers); 4 units of 808 sq ft carpet (2 towers); 2 units of 809 sq ft carpet (2 towers); 2 units of 814 sq ft carpet (3 towers); 34 units of 861 sq ft carpet (3 towers); 93 units of 880 sq ft carpet (2 towers); 2 units of 943 sq ft carpet (1 tower); 2 units of 953 sq ft carpet (2 towers); 2 units of 1,002 sq ft carpet (2 towers); 66 units of 1,076 sq ft carpet; 2 units of 1,132 sq ft carpet (3 towers); 34 units of 1,196 sq ft carpet (1 tower); 2 units of 1,270 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 26-10-2015 |
| Building plans approved on | 26-10-2015 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 20-06-2018 |
|---|---|
| Likely completion date | 30-09-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against METRO TECHNO BUILD PVT. LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in