Projects · MRG GROUP INDIA PVT. LTD.
MRG Crown
MRG Group India · Sector 58, Gurugram
Registered with RERA: Mar 2023
Is it legal?
- RERA registered, valid till Nov 2027
- HRERA opened a case of its own against the builder in Aug 2023 (closed):
- Why: did not submit approval of service plans and estimates within three months
- Latest: case disposed by final judgement on 22 Mar 2024
- At stake: service plans security liable to forfeiture; ₹25 lakh environmental security to be refunded
Will it be delivered on time?
- Deadline Apr 2027, never extended
- No occupation certificate yet (not ready for possession)
- Construction 68% complete (architect, Jul–Sep 2026)
- Money: ₹285.6 crore spent of ₹443.6 crore; ₹158 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 436 units: 300 sold, 136 unsold (builder's certificate, Sep 2026)
- Apartment: 300 of 436 sold
- Commercial Shops: 0 of 0 sold
- EWS: 0 of 0 sold
- 436 units in 6 sizes, as declared to HRERA:
- 96 units of 781 sq ft carpet
- 136 units of 888 sq ft carpet
- 32 units of 899 sq ft carpet
- 108 units of 948 sq ft carpet
- 48 units of 952 sq ft carpet (12 towers)
- 16 units of 965 sq ft carpet
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
- 109 plots, 155–179 sq yd
Location
- Nearest metro: Sector 55–56, 1.5 km by road (7 min by car)
- Cyber City 31 min · Airport 48 min by car at 9:30 am
- Within 3 km: 7 hospitals, 10 schools, 1 mall
The builder: MRG Group India
- 3 projects registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
★ MRG Group India was earlier called Anudhara Solutions Private Limited. Its history under the earlier name matters too: 0 projects, 0 decided buyer complaints.
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | MRG CROWN |
|---|---|
| Builder (promoter) | MRG GROUP INDIA PVT. LTD. |
| Location | 9TH FLOOR, IREO GRAND VIEW TO WER, SECTOR-58, GURUGRAM |
| RERA project ID | RERA-GRG-1324-2023 |
| Registration certificate number | GGM/706/438/2023/50 DATED 29.03.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 15/11/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 3.8 acres |
| Licence | 192 of 2022 |
| Estimated cost of the project | ₹47,497.06 lakh (₹474.97 crore) |
| Total units (plots, apartments, shops) | 545 |
| Unit sizes (carpet area, as declared) | 96 units of 781 sq ft carpet; 136 units of 888 sq ft carpet; 32 units of 899 sq ft carpet; 108 units of 948 sq ft carpet; 48 units of 952 sq ft carpet (12 towers); 16 units of 965 sq ft carpet |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 24-11-2022 |
| Building plans approved on | 22-02-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-05-2023 |
|---|---|
| Likely completion date | 30-04-2027 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 29-Oct-2026 |
| Quarterly reports listed on the portal | 14 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,732.86 lakh (₹17.33 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,298.14 lakh (₹12.98 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹335.12 lakh (₹3.35 crore) |
| Project bank account (escrow): deposited in the quarter | ₹1,246.66 lakh (₹12.47 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹1,246.66 lakh (₹12.47 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 436 apartments |
| Sold in the quarter | 16 apartments |
| EDC (development charges): paid / due as on date | ₹1,346.48 lakh (₹13.46 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026 |
|---|---|
| Overall work complete | 68% |
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Disposed: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against MRG GROUP INDIA PVT. LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in