Projects · BNB COLONIZER PVT LTD
Nature Valley
Bnb Colonizer · Sector 70, Gurugram
Registered with RERA: Oct 2022
Is it legal?
- RERA registered, valid till May 2027
- HRERA opened a case of its own against the builder in Jan 2023 (still open):
- Why: did not comply with registration certificate conditions for Sector 70 project; service plan filed late
- Latest: promoter replied to show-cause notice 09 Mar 2026; case pending
- At stake: Proposed forfeiture of security and revocation of registration certificate; no penalty imposed yet
Will it be delivered on time?
- Deadline May 2027, never extended
- No occupation certificate yet (not ready for possession)
- Construction 100% complete (architect, Jul–Sep 2026)
What's on offer?
- 2 units sold (builder's certificate, Jul 2026)
- 80 plots, 107–179 sq yd
Location
- Nearest metro: Sector 55–56, 10.1 km by road (37 min by car)
- Cyber City 57 min · Airport 47 min by car at 9:30 am
- Within 3 km: 7 hospitals, 2 schools, 2 malls
The builder: Bnb Colonizer
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | NATURE VALLEY |
|---|---|
| Builder (promoter) | BNB COLONIZER PVT LTD |
| Location | SECTOR 70, BADSHAHPUR |
| RERA project ID | RERA-GRG-1034-2022 |
| Registration certificate number | GGM/613/345/2022/88 DATED 03.10.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 12/05/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.01875 acres |
| Licence | 61 of 2022 Dated 13-05-2022 by TCP |
| Estimated cost of the project | ₹2,828.43 lakh (₹28.28 crore) |
| Total units (plots, apartments, shops) | 80 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 13-05-2022 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-10-2022 |
|---|---|
| Likely completion date | 12-05-2027 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2026 |
| Quarterly reports listed on the portal | 15 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹308.01 lakh (₹3.08 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹34.37 lakh (₹0.34 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹215.6 lakh (₹2.16 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹230.6 lakh (₹2.31 crore) |
| Project bank account (escrow): balance at quarter end | ₹8.1 lakh (₹0.08 crore) |
| Units in the project (apartments / plots) | 80 plots |
| Sold in the quarter | 1 plots |
| EDC (development charges): paid / due as on date | ₹599.11 lakh (₹5.99 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Mar 2025, for 31 Mar 2025 |
|---|---|
| Overall work complete | 100% |
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against BNB COLONIZER PVT LTD (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in