Projects · NEO DEVELOPERS PVT.LTD.
Neo Square
Neo Developers · Sector 109, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Feb 2025)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report, prompting show-cause notice (May 2022, open)
- Did not apply to extend registration or submit completion or occupation certificate, or requisite documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
- 256 complaints about this project decided by HRERA since Nov 2023 (7 delay interest ordered, 44 refund ordered, 189 assured return ordered, 4 other orders, 12 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline Aug 2021, extended 3 times to Feb 2025
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Oct–Dec 2025):
- Done: Energy management
- In progress: Tower c: sub structure 99%, Tower c: super structure 99%, Internal roads and pavements 95%, Storm water drains 95%, Rain water harvesting, percolating well/pit 95%, Tower c: finishing internal 89.46%, and 14 more
- Money: ₹220.5 crore spent of ₹233.8 crore; ₹13.3 crore still to spend (CA certificate, Dec 2025)
What's on offer?
- 659 units: 576 sold, 83 unsold (builder's certificate, Dec 2025)
- Registration now covers 659
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 6.8 km by road (10 min by car)
- Cyber City 49 min · Airport 27 min by car at 9:30 am
- Within 3 km: 6 hospitals, 3 schools, 1 mall
The builder: Neo Developers
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 314 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | NEO SQUARE |
|---|---|
| Builder (promoter) | NEO DEVELOPERS PVT.LTD. |
| Location | VILLAGE PAWALA KHUSRPUR,SECTO R-109, GURUGRAM |
| RERA project ID | RERA-GRG-545-2020 |
| Registration certificate number | 109 OF 2017 DATED 24.08.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 22/02/2025 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 8.237 acres |
| Licence | 102 of 2008 |
| Estimated cost of the project | ₹25,522.88 lakh (₹255.23 crore) |
| Total units (plots, apartments, shops) | 579 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 499 |
| Units unsold when registered | 80 |
| Layout plan approved on | 16-10-2019 |
| Building plans approved on | 16-10-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 23-08-2021 |
|---|---|
| Revised completion date | 23-08-2021 |
| Infrastructure: projected completion | 28-02-2021 |
| Infrastructure: percentage complete when registered | 20% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2025 (OCT-DEC) |
| Latest report submitted on | 04-Apr-2026 |
| Quarterly reports listed on the portal | 29 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹7.71 lakh (₹0.08 crore) |
| Spent on infrastructure in the quarter | ₹0.79 lakh (₹0.01 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹198.82 lakh (₹1.99 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹11.2 lakh (₹0.11 crore) |
| Units in the project (apartments / plots) | 659 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 10 Feb 2026, for 31 Dec 2025 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in