Projects · OCUS SKYCRAPERS REALTY LTD
Ocus 24K ( Commercial Colony)
Ocus Skycrapers Realty · Sector 68, Gurugram
Registered with RERA: Sep 2017
Is it legal?
- RERA registered, valid till Sep 2022 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Suspected late completion certificate; OC obtained 17 Jul 2019, before expiry, CC after expiry (Jul 2023, open). At stake: Warned of bank account freezing and sale restrictions if no reply; no penalty imposed
- Did not submit the quarterly progress report, so the Authority issued a show-cause notice (May 2022, open)
- Did not file REP-I (Part A-H) project updates or quarterly progress reports for Ocus 24K (Nov 2019, open). At stake: proposed ₹25,000 daily penalty from 31 Dec 2019, capped at 5% of project cost
- 2 more cases: reply 4
- 2 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 1 refund ordered)
Will it be delivered on time?
- Deadline Jul 2019, never extended (date has passed)
- Occupation certificate (Jul 2019) covers: Commercial building in Sector-68, Gurugram, with basements (no flats listed)
- Construction 100% complete (architect, Jul–Sep 2023)
- Money: ₹186.9 crore spent of ₹203 crore; ₹16.1 crore still to spend (CA certificate, Sep 2023)
What's on offer?
- 760 units: 320 sold, 440 unsold (builder's certificate)
Location
- Nearest metro: Sector 55–56, 8.4 km by road (28 min by car)
- Cyber City 53 min · Airport 55 min by car at 9:30 am
- Within 3 km: 8 hospitals, 8 schools, 5 malls
The builder: Ocus Skycrapers Realty
- 2 projects registered in Gurugram
- 2 with an occupation certificate on record
- 28 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | OCUS 24K ( COMMERCIAL COLONY) |
|---|---|
| Builder (promoter) | OCUS SKYCRAPERS REALTY LTD |
| Location | SECTOR-68, BADSHAHPUR, GURUGR AM |
| RERA project ID | RERA-GRG-424-2019 |
| Registration certificate number | 220 OF 2017 DATED 18.09.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 17/09/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 17968.014 acres |
| Licence | 76 OF 2012 |
| Estimated cost of the project | ₹24,561 lakh (₹245.61 crore) |
| Total units (plots, apartments, shops) | Not found in the records checked |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-01-2014 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2014 |
|---|---|
| Likely completion date | 31-07-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2023 (JUL-SEP) |
| Latest report submitted on | 15-May-2024 |
| Quarterly reports listed on the portal | 20 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2023 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹34.88 lakh (₹0.35 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹34.88 lakh (₹0.35 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 760 apartments |
| Sold in the quarter | 2 apartments |
| EDC (development charges): paid / due as on date | ₹1,621.67 lakh (₹16.22 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | for 30 Sep 2023 |
|---|---|
| Overall work complete | 100% |
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 2 |
|---|---|
| Cases |
|
| Decided cases against OCUS SKYCRAPERS REALTY LTD (all its projects) | 28 (Complaint: 26; Compensation: 2) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in