RERA’d by NeevHQ

Projects · OCUS SKYCRAPERS REALTY LTD

Ocus 24K ( Commercial Colony)

Ocus Skycrapers Realty · Sector 68, Gurugram

Registered with RERA: Sep 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Ocus Skycrapers Realty

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameOCUS 24K ( COMMERCIAL COLONY)
Builder (promoter)OCUS SKYCRAPERS REALTY LTD
LocationSECTOR-68, BADSHAHPUR, GURUGR AM
RERA project IDRERA-GRG-424-2019
Registration certificate number220 OF 2017 DATED 18.09.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to17/09/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area17968.014 acres
Licence76 OF 2012
Estimated cost of the project₹24,561 lakh (₹245.61 crore)
Total units (plots, apartments, shops)Not found in the records checked
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-01-2014
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2014
Likely completion date31-07-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2023 (JUL-SEP)
Latest report submitted on15-May-2024
Quarterly reports listed on the portal20

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2023 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹34.88 lakh (₹0.35 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹34.88 lakh (₹0.35 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)760 apartments
Sold in the quarter2 apartments
EDC (development charges): paid / due as on date₹1,621.67 lakh (₹16.22 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 19-01-2018
  • Demarcation Plan: Obtained Approval 01-08-2012
  • Zoning Plan: Obtained Approval 01-08-2012
  • Service Plans: Obtained Approval 08-03-2019
  • Electricity Plans: Obtained Approval 15-04-2019
  • Site Plans: Obtained Approval 08-03-2019
  • Building Plans: Obtained Approval 15-04-2019
  • Fire NOC: Obtained Approval 19-01-2018

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatefor 30 Sep 2023
Overall work complete100%
By part
  • OCUS 24K - Sub structure: 100%, Excavation, foundation, basements and waterproofing completed
  • OCUS 24K - Super structure: 100%, Ground+20th floor; slabs, walls, staircase and lift wells completed
  • OCUS 24K - Mechanical MEP (lifts, ventilation): 100%
  • OCUS 24K - Electrical MEP (conduiting, wiring, fixtures): 100%
  • OCUS 24K - Plumbing and firefighting MEP: 100%
  • OCUS 24K - Internal finishing: 100%, Plaster, tiling, flooring and painting completed
  • OCUS 24K - External finishing: 100%, External plaster, painting and facade completed
  • Common areas and services (Table B, B-1 items): 100%, Internal roads, parking, water supply, sewage, electrification, drainage, street lighting, security and fire fighting, STP, underground tank and electrical sub station all marked completed
Unclear in the certificate
  • The certificate date field is blank. The site inspection and certifying date is stated as 30-Sep-23.
  • The column for work done during the quarter shows dashes only, not a percentage, so the in-quarter figure is left null.
  • The overall 100% comes from the Total row of Table A, which is shown as 100.00%. The certificate does not state a separate overall figure in words.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; Pending: 2; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project2
Cases
Decided cases against OCUS SKYCRAPERS REALTY LTD (all its projects)28 (Complaint: 26; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in