Projects · CAPITAL HEIGHTS PRIVATE LIMITED
One Global
Capital Heights · Sector 73, Gurugram
Registered with RERA: Feb 2023
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Sep 2026)
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Original deadline Sep 2025, extended to Sep 2026
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Apr–Jun 2026):
- In progress: Sub structure 99%, Plumbing & firefighting 88%, Super structure 85%, Electrical 80%, Internal finishing 45%, External finishing 45%, and 1 more
- Money: ₹79.4 crore spent of ₹158.4 crore; ₹79 crore still to spend (CA certificate, Mar 2026)
What's on offer?
- 82 units: 70 sold, 12 unsold (builder's certificate, Jun 2026)
- Plot: 70 of 82 sold
- 84 plots, 101–246 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 19.6 km by road (52 min by car)
- Cyber City 59 min · Airport 49 min by car at 9:30 am
- Within 3 km: 1 hospital, 2 schools, 2 malls
Location shown for Sector 73; the exact site was not found.
The builder: Capital Heights
- 2 projects registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 11 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ONE GLOBAL |
|---|---|
| Builder (promoter) | CAPITAL HEIGHTS PRIVATE LIMITED |
| Location | SECTOR 73, VILLAGE BEGAMPUR K HATOLA |
| RERA project ID | RERA-GRG-1274-2023 |
| Registration certificate number | GGM/686/418/2023/30 DATED 02.02.2023 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/09/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 7.40625 acres |
| Licence | 184 OF 2022 Dated 14-11-2022 |
| Estimated cost of the project | ₹23,158.58 lakh (₹231.59 crore) |
| Total units (plots, apartments, shops) | 84 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 14-11-2022 |
| Building plans approved on | 10-01-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2023 |
|---|---|
| Likely completion date | 30-09-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/06/2026 (APR-JUN) |
| Latest report submitted on | 21-Aug-2026 |
| Quarterly reports listed on the portal | 13 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹314.78 lakh (₹3.15 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹231.13 lakh (₹2.31 crore) |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹248.55 lakh (₹2.49 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹297.36 lakh (₹2.97 crore) |
| Project bank account (escrow): deposited in the quarter | ₹126 lakh (₹1.26 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹126 lakh (₹1.26 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 82 plots |
| Sold in the quarter | 0 plots |
| EDC (development charges): paid / due as on date | ₹1,596.04 lakh (₹15.96 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 15 Apr 2026, for 31 Mar 2026 |
|---|---|
| By part |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against CAPITAL HEIGHTS PRIVATE LIMITED (all its projects) | 11 (Complaint: 10; Execution of an earlier order: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in