Projects · VATIKA ONE ON ONE PVT. LTD.
One On One PHASE-1
Vatika One On One · Sector 16, Gurugram
Registered with RERA: Sep 2017
Is it legal?
- RERA registered, valid till Sep 2022 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2023, open)
- Did not submit its quarterly progress report (May 2022, open)
- Received repeated notices for Section 42(1)D and QPR compliance; REP-I filing needed corrections (Nov 2019, open)
- 2 more cases: reply 4
- 8 complaints about this project decided by HRERA since Nov 2023 (8 assured return ordered)
Will it be delivered on time?
- Deadline Jul 2020, never extended (date has passed)
- Occupation certificate (Sep 2021) covers: Blocks 2, 3, 4 and 5 of commercial colony, Sector-16 (no flats listed)
- Construction, as certified by the architect (Jul–Sep 2025):
- Done: Substructure, Super structure, Mep, Finishing, Finishing
- Money: ₹624.1 crore spent of ₹633.4 crore; ₹9.3 crore still to spend (CA certificate, Sep 2025)
What's on offer?
- 1,098 units: 793 sold, 305 unsold (builder's certificate, Sep 2025)
- Apartment: 793 of 1098 sold
Location
- Nearest metro: IFFCO Chowk, 4 km by road (13 min by car)
- Cyber City 24 min · Airport 32 min by car at 9:30 am
- Within 3 km: 39 hospitals, 11 schools, 5 malls
Location shown for Sector 16; the exact site was not found.
The builder: Vatika One On One
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 81 buyer complaints decided by HRERA
★ Vatika One On One was earlier called Calder Developers Pvt. Ltd. Its history under the earlier name matters too: 0 projects, 0 decided buyer complaints.
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ONE ON ONE PHASE-1 |
|---|---|
| Builder (promoter) | VATIKA ONE ON ONE PVT. LTD. |
| Location | SECTOR 16, VILLAGE SILOKHERA, TEHSIL AND DIST GURUGRAM |
| RERA project ID | RERA-GRG-484-2019 |
| Registration certificate number | 237 OF 2017 DATED 20.09.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 19/09/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 49093.349 acres |
| Licence | . 5 of 2015 dated 06.08.2015 |
| Estimated cost of the project | ₹63,342 lakh (₹633.42 crore) |
| Total units (plots, apartments, shops) | 1098 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 632 |
| Units unsold when registered | 466 |
| Layout plan approved on | 18-05-2017 |
| Building plans approved on | 18-05-2017 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-07-2020 |
|---|---|
| Revised completion date | 31-07-2020 |
| Infrastructure: projected completion | 31-07-2020 |
| Infrastructure: percentage complete when registered | 9.12% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2025 (JUL-SEP) |
| Latest report submitted on | 29-Oct-2025 |
| Quarterly reports listed on the portal | 28 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2025 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹22,500 lakh (₹225 crore) |
| Spent on infrastructure in the quarter | ₹2,500 lakh (₹25 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹22,210.95 lakh (₹222.11 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0.55 lakh (₹0.01 crore) |
| Units in the project (apartments / plots) | 1098 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹2,634.89 lakh (₹26.35 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2025, for 30 Sep 2025 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in