Projects · HOMETOWN PROPERTIES PVT. LTD.

Oodles Skywalk

Hometown Properties · Village Sihi, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

Location

The builder: Hometown Properties

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameOODLES SKYWALK
Builder (promoter)HOMETOWN PROPERTIES PVT. LTD.
LocationVILLAGE SIHI, GURUGRAM
RERA project IDRERA-GRG-380-2019
Registration certificate number294 OF 2017 DATED 13.10.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2019
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area3.0326 acres
Licence08 of 2013(05-03-2013)
Estimated cost of the project₹12,452.18 lakh (₹124.52 crore)
Total units (plots, apartments, shops)470
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered199
Units unsold when registered271
Layout plan approved on17-05-2014
Building plans approved on17-01-2014

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2019
Revised completion date31-12-2020
Infrastructure: projected completion31-12-2020
Infrastructure: percentage complete when registered85%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 3; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project18
Cases
Decided cases against HOMETOWN PROPERTIES PVT. LTD. (all its projects)26 (Complaint: 22; Compensation: 4)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026