Projects · APEX BUILDWELL PVT. LTD.
Our Homes
Apex Buildwell · Sector 37C, Gurugram
Registered with RERA: Jul 2019
Is it legal?
- RERA registered, valid till Dec 2019 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report (May 2022, open)
- Did not apply to extend registration or submit completion, part completion or occupation certificate (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
- 55 complaints about this project decided by HRERA since Nov 2023 (33 delay interest ordered, 6 refund ordered, 1 other order, 15 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Dec 2019, never extended (date has passed)
- 5 occupation certificates issued:
- Nov 2019: Two certificates: 1,136 flats in 26 towers, 132 shops (1,136 flats)
- Nov 2019: 10 residential towers, 432 dwelling units, plus basement and stilt (432 flats)
- Nov 2019: Residential towers and shops in Sector 37-C
- Feb 2020: 16 residential towers (704 flats) and 132 shops (704 flats)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
Location
- Nearest metro: Millennium City Centre Gurugram, 14.3 km by road (46 min by car)
- Cyber City 52 min · Airport 38 min by car at 9:30 am
- Within 3 km: 17 hospitals, 6 schools, 1 mall
The builder: Apex Buildwell
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 214 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | OUR HOMES |
|---|---|
| Builder (promoter) | APEX BUILDWELL PVT. LTD. |
| Location | SECTOR-37C, GURUGRAM |
| RERA project ID | RERA-GRG-257-2019 |
| Registration certificate number | GGM/346/78/2019/40 DATED 08.07.2019 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 01/12/2019 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 10.144 acres |
| Licence | 13 of 2012 |
| Estimated cost of the project | ₹16,970.47 lakh (₹169.7 crore) |
| Total units (plots, apartments, shops) | 1471 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | 1154 |
| Units unsold when registered | 317 |
| Layout plan approved on | 07-05-2013 |
| Building plans approved on | 07-05-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 02-06-2017 |
|---|---|
| Revised completion date | 01-12-2019 |
| Infrastructure: projected completion | 30-11-2019 |
| Infrastructure: percentage complete when registered | 65% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in