Oyster Grande-Tower G

Adani M2K Projects · Sector 102, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

Location

The builder: Adani M2K Projects

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameOYSTER GRANDE-TOWER G
Builder (promoter)ADANI M2K PROJECTS LLP
LocationSECTOR 102/102A, VILLAGE KHED KI MAZRA, GURUGRAM
RERA project IDRERA-GRG-544-2019
Registration certificate number37 OF 2017 DATED 10.08.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to30/09/2024
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area0.2401 acres
Licence29 of 2012 (10-04-2012)
Estimated cost of the project₹13,653 lakh (₹136.53 crore)
Total units (plots, apartments, shops)58
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered2
Units unsold when registered56
Layout plan approved on27-04-2012
Building plans approved on27-04-2012

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-09-2024
Revised completion date30-09-2024
Infrastructure: projected completion30-09-2024
Infrastructure: percentage complete when registered30%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against ADANI M2K PROJECTS LLP (all its projects)16 (Complaint: 15; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026