Palash Tower (Tower-C)

Raheja Developers · Sector 99A, Gurugram

Registered with RERA: Feb 2018

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 99A; the exact site was not found.

The builder: Raheja Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project namePALASH TOWER (TOWER-C)
Builder (promoter)RAHEJA DEVELOPERS LTD
LocationSECTOR 99A
RERA project IDRERA-GRG-521-2019
Registration certificate number7(A) OF 2018 DATED 01.02.2018
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.28 acres
Licence64 of 2013 and 72 of 2014
Estimated cost of the project₹10,141 lakh (₹101.41 crore)
Total units (plots, apartments, shops)140
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder1 BHK: 599 sq ft carpet, 2 units; 2 BHK: 807 sq ft carpet, 64 units; 3 BHK: 984 sq ft carpet, 46 units; 3 BHK + servant room: 1,153 sq ft carpet, 16 units (source: the builder's registration form (Form A-H))
Units booked when registered59
Units unsold when registered81
Layout plan approved on15-12-2017
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date29-11-2022
Revised completion date31-12-2022
Infrastructure: projected completion31-12-2022
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2025 (APR-JUN)
Latest report submitted on28-Aug-2025
Quarterly reports listed on the portal27

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2025 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,740.41 lakh (₹17.4 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹2,751.11 lakh (₹27.51 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)140 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹482.32 lakh (₹4.82 crore) paid; ₹1,187.22 lakh (₹11.87 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 01-08-2014
  • Zoning Plan: Obtained Approval 01-08-2014
  • Service Plans: Obtained Approval 23-11-2017
  • Electricity Plans: Obtained Approval 23-11-2017
  • Site Plans: Obtained Approval 02-01-2017
  • Building Plans: Obtained Approval 02-01-2017
  • Fire NOC: Obtained Approval 06-03-2019

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 23 Jul 2025, for 30 Jun 2025
By part
  • Tower C: excavation: 100%
  • Tower C: raft foundation: 0%
  • Non-tower footings: 10%
  • Basement level 1: 100%
  • Tower C: waterproofing of sub-structure: 100%
  • Tower C: superstructure (G+19 floors): 65%
  • Tower C: ground floor: 100%
  • Tower C: slabs laid (G+19): 65%
  • Tower C: walls on floors: 68%
  • Tower C: staircase: 60%
  • Tower C: lift walls: 60%
  • Tower C: waterproofing of lift wells: 0%
  • Tower C: lift lobbies and common areas: 60%
  • Tower C: electrical works within flats (internal wiring): 20%
  • Tower C: plumbing works within flats: 0%
  • Tower C: external and internal wall finishing: 0%
  • Tower C: wall tiling and flooring: 0%
  • Tower C: lifts installation: 0%
  • Tower C: waterproofing of terraces: 0%
  • Tower C: entrance lobby finishing: 0%
  • Compound wall: 0%
  • Internal roads and pavements: 0%
  • Parking (covered and open): 0%
  • Water supply: 0%
  • Sewerage: 0%
  • Storm water drains: 0%
  • Landscaping and tree plantation: 0%
  • Parks and playgrounds: 0%
  • Street lighting and electrification: 0%
  • Solid waste management: 0%
  • Rain water harvesting: 0%
  • Fire protection and fire safety: 0%
  • Electrical meter room, sub-station: 0%
  • Community centre: 0%
  • Schools: 0%
Unclear in the certificate
  • Table A shows the tower raft at 0% under foundation but 100% under waterproofing of the sub-structure.
  • Lift lobbies and common areas are shown at 60% in item 9 but 55% in item 15.
  • Lift wells are shown at 60% in item 9 but 100% in item 15.
  • Table A lists total floors as G+19 with 65% but does not state an overall percentage for the whole tower.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusFirst Hearing: 3; Online Complaint Not Yet Received At Office: 1; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against RAHEJA DEVELOPERS LTD (all its projects)320 (Complaint: 252; Compensation: 32; Execution of an earlier order: 36)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in