Projects · EMAAR MGF LAND LTD.

Palm Gardens

Emaar MGF Land · Sector 83, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Emaar MGF Land

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project namePALM GARDENS
Builder (promoter)EMAAR MGF LAND LTD.
LocationSECTOR-83, VILLAGE KHERKI DAU LLA, GURUGRAM, HARYANA
RERA project IDRERA-GRG-626-2020
Registration certificate number330 OF 2017 DATED 24.10.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2019
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area12.37 acres
Licence108 of 2010 dated 18/12/2010
Estimated cost of the project₹42,541 lakh (₹425.41 crore)
Total units (plots, apartments, shops)730
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder3 BHK: 1,095–1,249 sq ft carpet, 674 units; 5 BHK: 2,431–2,489 sq ft carpet, 23 units (source: the builder's registration form (Form A-H))
Units booked when registered715
Units unsold when registered15
Layout plan approved on22-03-2012
Building plans approved on22-03-2012

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2018
Revised completion date31-12-2019
Infrastructure: projected completion31-12-2019
Infrastructure: percentage complete when registered100%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on12-Jul-2026
Quarterly reports listed on the portal31

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹27,826 lakh (₹278.26 crore)
Other costs in the quarter (EDC, taxes, etc.)₹10,590 lakh (₹105.9 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹1.58 lakh (₹0.02 crore)
Units in the project (apartments / plots)728 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹5,937.78 lakh (₹59.38 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 20-07-2011
  • Zoning Plan: Obtained Approval 20-01-2011
  • Service Plans: Obtained Approval 29-01-2018
  • Electricity Plans: Obtained Approval 28-06-2022
  • Site Plans: Obtained Approval 31-10-2014
  • Building Plans: Obtained Approval 18-07-2016
  • Fire NOC: Obtained Approval 14-06-2019

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 02 Jan 2024, for Dec-23
By part
  • Plots (Table A, building/tower no. not stated): Sub structure, super structure, MEP and finishing are each shown as 0% of total proposed work. All detailed tasks are marked NA, meaning not started or not applicable.
  • Common areas and services (Table B): Internal roads, parking (open), water supply, sewerage, storm water drains, landscaping, benches, street lighting, sewage treatment, solid waste management and electrical meter room are shown as 100% done. Covered parking, parks and playgrounds, shopping area, rain water harvesting, solar energy and community buildings are marked NA.
Unclear in the certificate
  • Table A is headed 'Plots' and gives no tower or building number.
  • No single overall percentage of construction completed is stated in the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 2; First Hearing: 2; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project11
Cases
Decided cases against EMAAR MGF LAND LTD. (all its projects)1022 (Complaint: 321; Execution of an earlier order: 50; Compensation: 29); breakdown of the latest 400

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in