Palm Heights

Emaar MGF Land · Sector 77, Gurugram

Registered with RERA: Nov 2018

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Emaar MGF Land

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project namePALM HEIGHTS
Builder (promoter)EMAAR MGF LAND LTD.
LocationSECTOR-77, SIKHOPUR, GURUGRAM
RERA project IDRERA-GRG-645-2020
Registration certificate numberGGM/297/2018/29 DATED 29.11.2018
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to27/02/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area5.50 acres
Licence56 of 2009 62 of 2013
Estimated cost of the project₹31,000 lakh (₹310 crore)
Total units (plots, apartments, shops)297
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered0
Units unsold when registered0
Layout plan approved on21-04-2011
Building plans approved on21-04-2011

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-08-2022
Revised completion date31-08-2022
Infrastructure: projected completion31-08-2022
Infrastructure: percentage complete when registered70%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on13-Oct-2026
Quarterly reports listed on the portal31

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹17,047 lakh (₹170.47 crore)
Other costs in the quarter (EDC, taxes, etc.)₹2,512 lakh (₹25.12 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)297 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹7,095.93 lakh (₹70.96 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 18-11-2023
  • Zoning Plan: Obtained Approval 18-11-2013
  • Service Plans: Obtained Approval 17-06-2016
  • Electricity Plans: Obtained Approval 01-05-2021
  • Site Plans: Obtained Approval 18-01-2023
  • Building Plans: Obtained Approval 28-08-2015
  • Fire NOC: Obtained Approval 24-06-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 09 Jan 2024, for DEC-23
By part
  • Tower C: Status sheet shows 25 floors of slabs laid, walls, staircase, lift wells and lift lobbies complete, and MEP, plastering, tiling, flooring and installation marked complete. Table A gives 0% for sub structure, 2% for super structure, 2-3% for MEP and 3% for finishing, as a share of total proposed work.
  • Tower D: Table A only. Sub structure shows 0% work done in the quarter, with 398.67 cumulative value. Super structure is 2%, MEP 2-3%, internal finishing 3% and external finishing 3% of total proposed work.
Unclear in the certificate
  • The certificate does not state one overall percentage of completion for the project or for any tower, so the percentage fields are left null.
  • Table A figures for Tower C (2-3% of total proposed work) do not match the Tower C status sheet, which shows many tasks at 100%. It is not clear from the document which measure applies.
  • The project is described as Towers B16-01, B16-02 and B-17 (Tower C, D and E), but only Tower C and Tower D have progress tables. No data is given for Tower E or the B16 blocks.
  • Work done values in Table A are given in figures without units stated on the pages.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusFirst Hearing: 5; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against EMAAR MGF LAND LTD. (all its projects)1022 (Complaint: 321; Execution of an earlier order: 50; Compensation: 29); breakdown of the latest 400

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026