The builder: Emaar MGF Land

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project namePALM SELECT
Builder (promoter)EMAAR MGF LAND LIMITED
LocationSECTOR 77 SHIKHOPUR GURUGRAM
RERA project IDRERA-GRG-445-2019
Registration certificate numberGGM/382/114/2019/76 DATED 24.12.2019
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/08/2021
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area3.29 acres
Licence56 of 2009 62 of 2013
Estimated cost of the project₹4,046 lakh (₹40.46 crore)
Total units (plots, apartments, shops)66
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder3 BHK: 1,034 sq ft carpet, 66 units (source: the builder's registration form (Form A-H))
Units booked when registered0
Units unsold when registered66
Layout plan approved on28-08-2015
Building plans approved on23-10-2018

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2022
Revised completion date31-12-2022
Infrastructure: projected completion31-12-2022
Infrastructure: percentage complete when registered60%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on13-Oct-2026
Quarterly reports listed on the portal27

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹2,892 lakh (₹28.92 crore)
Other costs in the quarter (EDC, taxes, etc.)₹532 lakh (₹5.32 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)66 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹7,095.93 lakh (₹70.96 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 22-07-2013
  • Zoning Plan: Obtained Approval 22-07-2013
  • Service Plans: Obtained Approval 17-11-2016
  • Electricity Plans: Obtained Approval 17-11-2016
  • Site Plans: Obtained Approval 26-02-2018
  • Building Plans: Obtained Approval 23-10-2018
  • Fire NOC: Obtained Approval 19-04-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 06 Jan 2024, for Dec-23
By part
  • Tower 60: Architect's checklist marks all listed sub-structure and super-structure tasks as completed, with 100% of proposed work shown. Tower has G+11 floors and all slabs laid by end of quarter. Lift installation, overhead tanks, underground water tank, fire-fighting equipment, entrance lobby and compound wall are marked completed.
  • Tower 62: not stated
Unclear in the certificate
  • Table A gives a 'percentage of work done to total proposed work' of 0% for every component of Tower 60 and Tower 62, while the same Tower 60 checklist marks tasks as 100% complete. The overall percentage for each tower is therefore not clear and is left as null.
  • Table A gives cumulative work done values (in the certificate's units) for each component, but no overall percentage figure for the project is stated.
  • Table B is referred to in the certificate but is not in the document, so the work done for any other buildings is not known.
  • The certificate states the work done in the quarter as negative values in brackets for several components, which is not explained.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed3
By statusScrutinized: 1; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against EMAAR MGF LAND LIMITED (all its projects)1022 (Complaint: 321; Execution of an earlier order: 50; Compensation: 29); breakdown of the latest 400

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026