Park Generation (Group Housing Project)
BPTP · Sector 37D, Gurugram
Registered with RERA: Jan 2018
Is it legal?
- RERA registered, valid till Aug 2019 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit quarterly progress report; show-cause notice issued 31 May 2022 (May 2022, open)
- Did not submit completion, part completion or occupation certificate after registration extension expired (Jun 2022, open)
- Did not file project updates (REP-I Part A to H) on the Authority's web portal (Nov 2019, open). At stake: penalty ₹25,000 per day, capped at five percent of project cost; no final amount
- 2 more cases: reply 4
- 1 complaint about this project decided by HRERA since Nov 2023 (1 delay interest ordered)
Will it be delivered on time?
- Deadline Apr 2018, never extended (date has passed)
- 2 occupation certificates issued:
- Sep 2019: Towers 14, 15, 18 and EWS block (225 flats)
- Apr 2023: Commercial block G+9 and basements 1 and 2 (no flats listed)
- Money: ₹249.7 crore spent of ₹253 crore; ₹3.3 crore still to spend (CA certificate, Dec 2024)
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 3 BHK: 902–1,142 sq ft carpet, 225 units
Location
- Nearest metro: Millennium City Centre Gurugram, 15.4 km by road (48 min by car)
- Cyber City 54 min · Airport 37 min by car at 9:30 am
- Within 3 km: 7 hospitals, 4 schools, 2 malls
The builder: BPTP
- 10 projects registered in Gurugram
- 4 with an occupation certificate on record
- 584 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | PARK GENERATION (GROUP HOUSING PROJECT) |
|---|---|
| Builder (promoter) | BPTP LIMITED |
| Location | SECTOR- 37D, GURUGRAM |
| RERA project ID | RERA-GRG-660-2020 |
| Registration certificate number | 07 OF 2018 DATED 03.01.2018 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/08/2019 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 26542.55 acres |
| Licence | 83 of 2008 and License no 94 of 2011 |
| Estimated cost of the project | ₹11,144.2 lakh (₹111.44 crore) |
| Total units (plots, apartments, shops) | 225 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 3 BHK: 902–1,142 sq ft carpet, 225 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 215 |
| Units unsold when registered | 10 |
| Layout plan approved on | 21-09-2012 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2016 |
|---|---|
| Revised completion date | 30-04-2018 |
| Infrastructure: projected completion | 30-04-2018 |
| Infrastructure: percentage complete when registered | 100% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2024 (OCT-DEC) |
| Latest report submitted on | 21-Mar-2025 |
| Quarterly reports listed on the portal | 25 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2024 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹411.46 lakh (₹4.11 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹46.97 lakh (₹0.47 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹3.36 lakh (₹0.03 crore) |
| Project bank account (escrow): deposited in the quarter | ₹288.03 lakh (₹2.88 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹288.03 lakh (₹2.88 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 450 apartments |
| Sold in the quarter | 4 apartments |
| EDC (development charges): paid / due as on date | ₹2,122.24 lakh (₹21.22 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 08 Jan 2025, for 31 Dec 2024 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against BPTP LIMITED (all its projects) | 584 (Complaint: 292; Compensation: 19; Execution of an earlier order: 89); breakdown of the latest 400 |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in