Park Street

Ks Propmart · Sector 85, Gurugram

Registered with RERA: Jul 2019

Is it legal?

Will it be delivered on time?

Location

The builder: Ks Propmart

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project namePARK STREET
Builder (promoter)KS PROPMART PVT. LTD.
LocationSECTOR-85, GURUGRAM
RERA project IDRERA-GRG-216-2019
Registration certificate numberGGM/347/79/2019/41 DATED 30.07.2019
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to30/06/2023
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.85 acres
Licence100 OF 2013
Estimated cost of the project₹22,064 lakh (₹220.64 crore)
Total units (plots, apartments, shops)439
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered174
Units unsold when registered265
Layout plan approved on02-12-2013
Building plans approved on01-05-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2019
Revised completion date31-12-2021
Infrastructure: projected completion31-12-2021
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusScrutinized: 1; First Hearing: 2; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project27
Cases
Decided cases against KS PROPMART PVT. LTD. (all its projects)43 (Complaint: 38; Compensation: 2; Execution of an earlier order: 3)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026