Projects · KEYWEST EDUINFRA & SERVICES PRIVATE LIMITED
Parq
Keywest Eduinfra & Services · Sector 80, Gurugram
Registered with RERA: Apr 2024
Is it legal?
- RERA registered, valid till May 2031
- HRERA opened a case of its own against the builder in Nov 2024 (closed):
- Why: obtained environmental clearance late (due 22 Aug 2024, obtained 09 Sep 2024) after conditional registration
- Latest: builder made submission 03 Mar 2026 on 09 Feb 2026 Tribunal order
- At stake: Security amount deposited for environmental clearance forfeited to Authority; amount not stated
Will it be delivered on time?
- Deadline Feb 2030, never extended
- No occupation certificate yet (not ready for possession)
- Money: ₹473 crore spent of ₹924.7 crore; ₹451.7 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- Sizes declared at registration (533 units):
- 78 units averaging about 180 sq ft carpet
- 52 units averaging about 220 sq ft carpet
- 45 units averaging about 250 sq ft carpet
- 49 units averaging about 280 sq ft carpet
- 29 units averaging about 470 sq ft carpet
- 80 units of 2,207 sq ft carpet
- 6 less common sizes: see the full list below
- 133 units: the size the builder entered is not possible, so it is not shown
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 18.8 km by road (48 min by car)
- Cyber City 54 min · Airport 45 min by car at 9:30 am
- Within 3 km: 2 hospitals, 0 schools, 0 malls
The builder: Keywest Eduinfra & Services
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | PARQ |
|---|---|
| Builder (promoter) | KEYWEST EDUINFRA & SERVICES PRIVATE LIMITED |
| Location | VILLAGE NAURANGPUR, SECTOR-80 |
| RERA project ID | RERA-GRG-1584-2024 |
| Registration certificate number | GGM/818/550/2024/45 DATED 22.04.2024 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/05/2031 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.6 acres |
| Licence | . 244 of 2023 granted by Town and Country Planning Department, Haryana Government |
| Estimated cost of the project | ₹1,05,534.48 lakh (₹1,055.34 crore) |
| Total units (plots, apartments, shops) | 533 |
| Unit sizes (carpet area, as declared) | 78 units averaging about 180 sq ft carpet; 52 units averaging about 220 sq ft carpet; 45 units averaging about 250 sq ft carpet; 49 units averaging about 280 sq ft carpet; 29 units averaging about 470 sq ft carpet; 27 units averaging about 500 sq ft carpet; 22 units averaging about 610 sq ft carpet; 7 units averaging about 1,450 sq ft carpet; 5 units of 1,848 sq ft carpet; 80 units of 2,207 sq ft carpet; 4 units averaging about 3,740 sq ft carpet; 2 units averaging about 6,030 sq ft carpet |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-09-2024 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-09-2024 |
|---|---|
| Likely completion date | 28-02-2030 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2026 |
| Quarterly reports listed on the portal | 9 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹4,310.8 lakh (₹43.11 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹1,615 lakh (₹16.15 crore) |
| Spent on construction of apartments in the quarter | ₹28,462.72 lakh (₹284.63 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹9,345.09 lakh (₹93.45 crore) |
| Project bank account (escrow): deposited in the quarter | ₹2,982.96 lakh (₹29.83 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹3,011.98 lakh (₹30.12 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 448 apartments |
| Sold in the quarter | 9 apartments |
| EDC (development charges): paid / due as on date | ₹988.25 lakh (₹9.88 crore) paid; ₹248.14 lakh (₹2.48 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 01 Oct 2026, for 01 Oct 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Disposed: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against KEYWEST EDUINFRA & SERVICES PRIVATE LIMITED (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in