Projects · MAGIC EYE DEVELOPERS PVT LTD
Plaza 106 DDJAY
Magic Eye Developers · Sector 106, Gurugram
Registered with RERA: May 2022
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Dec 2024)
- HRERA opened a case of its own against the builder in Aug 2025 (still open):
- Why: did not meet declared completion timeline for Plaza 106 DDJAY; no appearance 18 Dec 2025
- Latest: final opportunity 18 Dec 2025; next hearing 16 Jan 2026
- At stake: Penal proceedings if builder fails to appear; no amount stated
- 12 complaints about this project decided by HRERA since Nov 2023 (2 delay interest ordered, 8 refund ordered, 2 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Dec 2024, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- 98 plots, 91–678 sq yd
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 9.7 km by road (16 min by car)
- Cyber City 54 min · Airport 33 min by car at 9:30 am
- Within 3 km: 4 hospitals, 0 schools, 0 malls
The builder: Magic Eye Developers
- 4 projects registered in Gurugram, 2 lapsed
- 1 with an occupation certificate on record
- 63 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | PLAZA 106 DDJAY |
|---|---|
| Builder (promoter) | MAGIC EYE DEVELOPERS PVT LTD |
| Location | PLAZA 106 DDJAY , SECTOR 106, NEAR DAULTABAD VILLAGE, GURGAON |
| RERA project ID | RERA-GRG-953-2021 |
| Registration certificate number | GGM/556/288/2022/31 DATED 02.05.2022 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.35625 acres |
| Licence | .71 of 2021 |
| Estimated cost of the project | ₹8,659.17 lakh (₹86.59 crore) |
| Total units (plots, apartments, shops) | 98 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 17-09-2021 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-04-2022 |
|---|---|
| Likely completion date | 31-12-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in