Projects · FAITH BUILDTECH PRIVATE LIMITED
Pride Park
Faith Buildtech · Sector 4, Gurugram
Registered with RERA: Jun 2024
Is it legal?
- RERA registered, valid till Jan 2029
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Jan 2029, never extended
- No occupation certificate yet (not ready for possession)
- Construction 100% complete (architect, Oct–Dec 2025)
- Money: ₹89.4 crore spent of ₹104.7 crore; ₹15.3 crore still to spend (CA certificate, Dec 2025)
What's on offer?
- 330 units sold (builder's certificate)
- Residential Plots: 330 of 330 sold
- Commercial Block: 0 of 1 sold
- 330 units in 29 sizes, as declared to HRERA:
- 30 units of 1,065 sq ft carpet
- 29 units of 1,144 sq ft carpet
- 30 units of 1,154 sq ft carpet
- 21 units of 1,452 sq ft carpet
- 18 units of 1,484 sq ft carpet
- 122 units of 1,614 sq ft carpet
- 23 less common sizes: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Sector 55–56, 26.5 km by road (54 min by car)
- Cyber City 68 min · Airport 73 min by car at 9:30 am
- Within 3 km: 3 hospitals, 3 schools, 0 malls
The builder: Faith Buildtech
- 3 projects registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | PRIDE PARK |
|---|---|
| Builder (promoter) | FAITH BUILDTECH PRIVATE LIMITED |
| Location | SECTOR 4, VILLAGE - KHAIKA, S OHNA |
| RERA project ID | RERA-GRG-1515-2023 |
| Registration certificate number | GGM/841/573/2024/68 DATED 18.06.2024 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 17/01/2029 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 18.475 acres |
| Licence | 05 of 2024(18-01-2024) |
| Estimated cost of the project | ₹16,377.5 lakh (₹163.78 crore) |
| Total units (plots, apartments, shops) | 330 |
| Unit sizes (carpet area, as declared) | 2 units of 766 sq ft carpet; 3 units of 936 sq ft carpet; 2 units of 954 sq ft carpet; 3 units of 1,027 sq ft carpet; 30 units of 1,065 sq ft carpet; 10 units of 1,068 sq ft carpet; 1 unit of 1,075 sq ft carpet; 1 unit of 1,136 sq ft carpet; 2 units of 1,137 sq ft carpet; 4 units of 1,138 sq ft carpet; 4 units of 1,139 sq ft carpet; 1 unit of 1,141 sq ft carpet; 1 unit of 1,142 sq ft carpet; 29 units of 1,144 sq ft carpet; 30 units of 1,154 sq ft carpet; 4 units of 1,328 sq ft carpet; 1 unit of 1,426 sq ft carpet; 16 units of 1,448 sq ft carpet; 21 units of 1,452 sq ft carpet; 2 units of 1,458 sq ft carpet; 1 unit of 1,463 sq ft carpet; 18 units of 1,484 sq ft carpet; 1 unit of 1,511 sq ft carpet; 2 units of 1,533 sq ft carpet; 2 units of 1,580 sq ft carpet; 2 units of 1,609 sq ft carpet; 4 units of 1,612 sq ft carpet; 11 units of 1,613 sq ft carpet; 122 units of 1,614 sq ft carpet |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 19-01-2024 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-04-2024 |
|---|---|
| Likely completion date | 17-01-2029 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2025 (OCT-DEC) |
| Latest report submitted on | 10-Feb-2026 |
| Quarterly reports listed on the portal | 6 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹2,823.57 lakh (₹28.24 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹872.82 lakh (₹8.73 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹2,028.35 lakh (₹20.28 crore) |
| Project bank account (escrow): deposited in the quarter | ₹2,823.57 lakh (₹28.24 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹2,600.78 lakh (₹26.01 crore) |
| Project bank account (escrow): balance at quarter end | ₹222.79 lakh (₹2.23 crore) |
| Units in the project (apartments / plots) | 331 plots |
| Sold in the quarter | 31 plots |
| EDC (development charges): paid / due as on date | ₹1,488.72 lakh (₹14.89 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 07 Jan 2026, for 31 Dec 2025 |
|---|---|
| Overall work complete | 100% |
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against FAITH BUILDTECH PRIVATE LIMITED (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in