Projects · RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD.
Primera (Tower A-D) + EWS
Ramprastha Promoters And Developers · Sector 37, Gurugram
Registered with RERA: Oct 2018
Is it legal?
- RERA registered, valid till Sep 2025 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not apply to extend registration or submit completion, part completion or occupation certificate (Jun 2022, open)
- Did not complete the project within the time it declared (Jun 2022, open)
- Did not submit the quarterly progress report (May 2022, open)
- 3 more cases: reply 4
- 9 complaints about this project decided by HRERA since Nov 2023 (7 delay interest ordered, 1 refund ordered, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline Mar 2020, extended to Sep 2025
- The order keeps buyers' right to a refund or interest for the delay
- 3 occupation certificates issued:
- Apr 2023: Towers A, B, C, D, convenience shopping and EWS block
- Apr 2023: Towers A, B, C, D, shopping block and EWS block
- Apr 2023: Towers A, B, C, D, EWS Block and convenient shopping (487 flats)
What's on offer?
- 266 units sold (builder's certificate, Mar 2022)
- 3 BHK WITH STORE TYPE A: 140 sold
- 3BHK TYPE B: 116 sold
- 3BHK CONNECTOR TYPE C: 5 sold
- 3BHK CONNECTOR TYPE D: 5 sold
- EWS: 0 sold
- Registration now covers 368 residential flats, 119 EWS units and 6 commercial shops
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
Location
- Nearest metro: Millennium City Centre Gurugram, 11.4 km by road (38 min by car)
- Cyber City 44 min · Airport 42 min by car at 9:30 am
- Within 3 km: 22 hospitals, 6 schools, 1 mall
Location shown for Sector 37; the exact site was not found.
The builder: Ramprastha Promoters & Developers
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 45 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | PRIMERA (TOWER A-D) + EWS |
|---|
| Builder (promoter) | RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD. |
|---|
| Location | SECTOR 37-D, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-302-2019 |
|---|
| Registration certificate number | GGM/289/2018/21 DATED 23.10.2018 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/09/2025 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 15788.9 acres |
|---|
| Licence | 12 of 2009 |
|---|
| Estimated cost of the project | ₹22,847 lakh (₹228.47 crore) |
|---|
| Total units (plots, apartments, shops) | 493 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 3 BHK + store: 368 units (source: the builder's registration form (Form A-H)) |
|---|
| Units booked when registered | 260 |
|---|
| Units unsold when registered | 233 |
|---|
| Layout plan approved on | 25-01-2013 |
|---|
| Building plans approved on | 25-01-2013 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-03-2020 |
|---|
| Revised completion date | 31-03-2020 |
|---|
| Infrastructure: projected completion | 31-03-2020 |
|---|
| Infrastructure: percentage complete when registered | 30% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/03/2022 (JAN-MAR) |
|---|
| Latest report submitted on | 12-Jul-2022 |
|---|
| Quarterly reports listed on the portal | 13 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2022 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0.19 lakh (₹0 crore) |
|---|
| Units in the project (apartments / plots) | 487 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,151.32 lakh (₹11.51 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 18-05-2012
- Zoning Plan: Obtained Approval 24-01-2013
- Service Plans: Obtained Approval 18-01-2021
- Electricity Plans: Obtained Approval 18-01-2021
- Site Plans: Obtained Approval 18-09-2018
- Building Plans: Obtained Approval 25-04-2013
- Fire NOC: Obtained Approval 03-03-2022
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Unclear in the certificate | - The page says the project is almost complete and an occupancy certificate has been applied for. It gives no percentage figures and no quarter or date. The architect's certificate is to be submitted offline to RERA, Gurugram.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate: covers Towers A, B, C and D (ground floor to 22nd floor), Convenience Shopping and EWS Block in the group housing colony on about 13.156 acres in Sector-37D, Gurugram. The certificate is issued for the buildings as described in the approved table, subject to the listed conditions.. Addressed to Ramprastha Promoters and Developers Pvt. Ltd.. Unclear in the document: The issue date of the memo is illegible in the scan.; The composition fee amount is garbled in the scan and is not stated clearly.; The total number of dwelling units is garbled in the scan.; The promoter company name and the licence details are partly illegible.; The per-tower dwelling unit counts and area figures are partly garbled.; The signatory and the referenced memo numbers are partly illegible.
- Occupation Certificate: covers Towers A, B, C and D (ground floor to 22nd floor, 92 dwelling units each per the table), the Convenience Shopping block, and the EWS block (stilt/ground floor to 4th floor, 119 EWS units). Site is group housing on about 13.156 acres in Sector 37D, Gurugram, under Licence No. 12 of 2008.. Addressed to Ramprastha Promoters and Developers Pvt. Ltd.. Unclear in the document: Memo date and memo number are garbled in the scan, so the issue date could not be read.; Composition fee amount is garbled (reads like 9,67,8281). Not stated with certainty.; Total unit count line is garbled and the tower unit figures do not clearly add up to the total, so the dwelling unit total is not stated.; Convenience Shopping block row and some area figures are partly illegible.; Promoter name and licence year are partly garbled in the scan.
- Occupation Certificate (Form BR-VII) dated 05 Apr 2023: covers Tower-A, Tower-B, Tower-C, Tower-D, Convenient Shopping and EWS Block in the group housing colony measuring 13.156 acres (Licence No. 12 of 2009 dated 21.05.2009), Sector-37D, Gurugram. Towers A to D run from ground floor to 22nd floor. The EWS Block runs from stilt/ground floor to 4th floor. Convenient Shopping is ground floor only. Basements 1 to 3 are also listed. The certificate covers 368 main dwelling units and 119 EWS units.. Addressed to Ramprastha Promoters and Developers Pvt. Ltd.. Composition fees for variations from approved plans: ₹9,67,828
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Scrutinized: 1; First Hearing: 5 |
|---|
| Proceedings | - RERA-GRG-2147-2020: The Authority's own proceeding against the promoter, Ramprastha Promoters and Developers Pvt. Ltd., Gurugram. The page does not state the specific default or violation. Status: Scrutinized. No next hearing date is shown (NA). Latest: 14 Aug 2020, Case was listed in the complaint listing with a Dak ID of 9507 recorded. The listing remark reads HARERA NEW COMPLAINT.
- RERA-GRG-3390-2022: Complaint numbered RERA-GRG-3390-2022 listed under HARERA Gurugram through the complainant, against Ramprastha Promoters and Developers Pvt. Ltd. (the promoter). The page does not state the complaint's grounds. The page does not show that the Authority started the case itself. Status: First hearing was listed for 30 Jun 2022. The page shows the status as FIRST HEARING, with no proceedings or order recorded for that day. Latest: 30 Jun 2022, First hearing listed. The complainant submitted documents under Dak ID 36710. No proceedings or order are recorded on the page.
- RERA-GRG-3933-2022: Show cause notice issued by the Authority to the promoter for not applying to extend its registration and for not submitting a completion, part completion or occupation certificate, and for not submitting requisite documents. The case is listed as HARERA Gurugram against Ramprastha Promoters and Developers Pvt. Ltd., and the registration certificate is shown as expired. Status: At the first hearing stage. The page shows a first hearing on 28 Jun 2022 with no proceedings or order recorded, and no later hearing date is shown. Latest: 06 Jul 2023, Two documents were received. One was marked as wrongly submitted. The other, filed on behalf of one respondent, placed on record an Appellate Tribunal order dated 17 Nov 2021.
- RERA-GRG-3934-2022: Show-cause notice to the promoter for not completing the project within the time it declared, under section 4(2)(l)(C) of the RERA Act. The Authority started this case itself against Ramprastha Promoters and Developers Pvt. Ltd. Status: First hearing listed for 30 Jun 2022. The listing shows status 'First Hearing' with no proceedings, bench or order recorded, and no order uploaded. Latest: 30 Jun 2022, First hearing listed. No proceedings or order are recorded for this date.
- RERA-GRG-4281-2022: The Authority issued a show cause notice to the promoter, Ramprastha Promoters and Developers Pvt. Ltd., for not submitting a quarterly progress report. The Authority asked the promoter to appear for a first hearing and give a written reply. Status: First hearing listed for 27 Jun 2022. The page records no hearing outcome, proceedings or order. Latest: 27 Jun 2022, First hearing listed. The page shows the status as First Hearing, with no proceedings or order recorded.
- RERA-GRG-4304-2022: Project RC compliance hearing against Ramprastha Promoters and Developers Pvt. Ltd. in Gurugram. The case is listed as HARERA Gurugram through a named individual versus the promoter. The notice and hearing are recorded as project RC compliance hearings. Status: First hearing listed for 01 Jul 2022. The page records the status as FIRST HEARING, with no proceedings or order recorded. Latest: 01 Jul 2022, First hearing held. The page shows no proceedings of the day and no order.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 9 |
|---|
| Cases | - RERA-GRG-5880-2023 (complaint, decided 21-Aug-2025): Buyer sought delay possession charges and possession; builder ordered to pay 10.85% interest up to 08 Jun 2023 and hand over possession.
- RERA-GRG-2147-2024 (complaint, decided 30-Jul-2025): Buyers sought delay compensation and waiver of club and holding charges; HRERA ordered 11.10% delay interest from Feb 2018 to Jun 2023.
- RERA-GRG-4265-2024 (complaint, decided 21-Mar-2025): Buyer sought possession after delay; authority upheld cancellation and ordered refund of Rs 15.87 lakh with interest.
- RERA-GRG-335-2024 (complaint, decided 13-Feb-2025): Buyers sought delay possession charges for a flat in Primera, Gurugram; builder ordered to pay 11.10% interest on paid amount for delay.
- RERA-GRG-1214-2023 (complaint, decided 24-Oct-2024): Buyers sought delay possession charges and possession of Primera unit; builder ordered to pay 11.10% delay interest till 08.06.2023.
- RERA-GRG-4572-2023 (complaint, decided 13-Sep-2024): Buyer sought delay interest and possession after builder's delay; HRERA ordered possession handover, cancellation of illegal demands, and delay interest at 11.10%.
- RERA-GRG-2508-2023 (complaint, decided 01-Mar-2024): Buyer sought possession and delay interest; HRERA ordered builder to pay 10.85% interest for delay and hand over flat.
- RERA-GRG-2584-2023 (complaint, decided 01-Mar-2024): Buyers sought possession and delay interest after a delay of over five years; HRERA ordered possession within 30 days and interest at 10.85% p.a.
- RERA-GRG-251-2023 (complaint, decided 31-Jan-2024): Buyers sought possession and delay interest for a Gurugram flat; HRERA ordered builder to pay 10.85% interest for the delay and hand over the unit.
|
|---|
| Decided cases against RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD. (all its projects) | 196 (Complaint: 153; Execution of an earlier order: 32; Compensation: 11) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in