Projects · JASMINE BUILDMART PVT. LTD.
Provence Estate (PH-1, Tower A &B)
Jasmine Buildmart · Sector 2, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Mar 2019)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not file REP-I (Parts A to H) form for offline registered project (Jun 2022, open)
- Did not submit a quarterly progress report (May 2022, open)
- Did not submit completion, part completion or occupation certificate after registration extension lapsed (Jun 2022, open)
- 4 more cases: reply 4
- 3 complaints about this project decided by HRERA since Nov 2023 (2 refund ordered, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
Location
- Nearest metro: Sector 54 Chowk, 0.9 km by road (5 min by car)
- Cyber City 24 min · Airport 41 min by car at 9:30 am
- Within 3 km: 12 hospitals, 15 schools, 5 malls
The builder: Jasmine Buildmart
- 2 projects registered in Gurugram, 1 lapsed
- 1 with an occupation certificate on record
- 7 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | PROVENCE ESTATE (PH-1, TOWER A &B) |
|---|---|
| Builder (promoter) | JASMINE BUILDMART PVT. LTD. |
| Location | SECTOR 2 GURUGRAM |
| RERA project ID | Not shown on the portal (older interim registration) |
| Registration certificate number | 282 OF 2017 DATED 09.10.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/03/2019 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Not found in the records checked |
|---|
Source: not checked yet
Project details (from the registration form, Form A-H)
| Project type | Not found in the records checked |
|---|---|
| Land area | Not found in the records checked |
| Licence | Not found in the records checked |
| Estimated cost of the project | Not found in the records checked |
| Total units (plots, apartments, shops) | Not found in the records checked |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | Not found in the records checked |
| Building plans approved on | Not found in the records checked |
Source: not checked yet
Timeline declared by the builder
| Likely start of construction | Not found in the records checked |
|---|---|
| Likely completion date | Not found in the records checked |
Source: not checked yet
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 3 |
|---|---|
| Cases |
|
| Decided cases against JASMINE BUILDMART PVT. LTD. (all its projects) | 7 (Complaint: 7) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in