RERA’d by NeevHQ

Projects · PURI CONSTRUCTION PRIVATE LIMITED

Puri The Aravallis

Puri Construction · Sector 61, Gurugram

Registered with RERA: Jul 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Puri Construction

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project namePURI THE ARAVALLIS
Builder (promoter)PURI CONSTRUCTION PRIVATE LIMITED
LocationSECTOR 61, VILLAGE ULLAWAS
RERA project IDRERA-GRG-1049-2022
Registration certificate numberGGM/592/324/2022/67 DATED 18.07.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/06/2029
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area10 acres
Licence58 of 2017
Estimated cost of the project₹56,921.75 lakh (₹569.22 crore)
Total units (plots, apartments, shops)324
Unit sizes (carpet area, as declared)160 units of 1,250 sq ft carpet (2 towers); 4 units of 1,285 sq ft carpet (2 towers); 160 units of 1,627 sq ft carpet (2 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-04-2023
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-04-2023
Likely completion date30-06-2029

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal16

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹4,860.85 lakh (₹48.61 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹2,705.68 lakh (₹27.06 crore)
Spent on infrastructure in the quarter₹42.56 lakh (₹0.43 crore)
Other costs in the quarter (EDC, taxes, etc.)₹593.8 lakh (₹5.94 crore)
Project bank account (escrow): deposited in the quarter₹4,860.85 lakh (₹48.61 crore)
Project bank account (escrow): withdrawn in the quarter₹4,713.9 lakh (₹47.14 crore)
Project bank account (escrow): balance at quarter end₹198.18 lakh (₹1.98 crore)
Units in the project (apartments / plots)324 apartments
Sold in the quarter4 apartments
EDC (development charges): paid / due as on date₹4,287.79 lakh (₹42.88 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 07-01-2017
  • Zoning Plan: Obtained Approval 19-05-2022
  • Service Plans: Obtained Approval 22-08-2022
  • Electricity Plans: Obtained Approval 21-12-2022
  • Site Plans: Obtained Approval 31-05-2022
  • Building Plans: Obtained Approval 31-05-2022
  • Fire NOC: Obtained Approval 29-06-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Club building: 100%, All listed works, including sub-structure, super-structure, MEP, finishing and installations, are marked completed. Building has 2 floors.
  • Tower - A, B, Allied buildings etc.: 84.98%, Net cumulative work done excluding advances is 82.05%.
Unclear in the certificate
  • Table A2 gives percentages for the Tower A, B and allied buildings group (84.98%, or 82.05% excluding advances), not one overall figure for the whole project.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against PURI CONSTRUCTION PRIVATE LIMITED (all its projects)8 (Complaint: 7; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in