Projects · RAHEJA DEVELOPERS LTD.

Raheja Trinity

Raheja Developers · Sector 84, Gurugram

Registered with RERA: Jul 2017

Is it legal?

Will it be delivered on time?

Location

The builder: Raheja Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameRAHEJA TRINITY
Builder (promoter)RAHEJA DEVELOPERS LTD.
LocationSECTOR-84, GURUGRAM
RERA project IDRERA-GRG-387-2019
Registration certificate number24 OF 2017 DATED 25.07.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to25/07/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.281 acres
Licence26 of 2013
Estimated cost of the project₹24,100 lakh (₹241 crore)
Total units (plots, apartments, shops)268
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered83
Units unsold when registered185
Layout plan approved on31-10-2013
Building plans approved on31-10-2013

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date19-06-2019
Revised completion date31-12-2022
Infrastructure: projected completion31-12-2022
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2025 (JAN-MAR)
Latest report submitted on25-Apr-2025
Quarterly reports listed on the portal26

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,361.93 lakh (₹13.62 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹2,312.53 lakh (₹23.13 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹2.96 lakh (₹0.03 crore)
Units in the project (apartments / plots)268 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹646.44 lakh (₹6.46 crore) paid; ₹1,331.57 lakh (₹13.32 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 17-05-2013
  • Zoning Plan: Obtained Approval 17-05-2013
  • Electricity Plans: Obtained Approval 02-06-2014
  • Site Plans: Obtained Approval 31-10-2013
  • Building Plans: Obtained Approval 31-10-2013

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 05 Apr 2025, for 31 Mar 2025
By part
  • Excavation: 76%
  • Raft foundation: 69%
  • Basement level 1: 33%, Number of basements stated as 4
  • Basement level 2: 49%
  • Waterproofing of sub-structure: 18%
  • Total floors in tower/building: 20%
  • Total area on each floor: 13.5%
  • Stilt floor / ground floor: 30%
  • Laying of slabs floor wise: 30%, Slab count is unclear, see unclear notes
  • Status of construction: 20%
  • Walls on floors: 36%
  • Staircase: 16%
  • Lift wells along with water proofing: 16%
  • Lift lobbies / common areas floor wise: 0%
Unclear in the certificate
  • The certificate does not name individual towers or blocks; the figures appear to apply to the project/phase as a whole.
  • The Dated and Place fields are blank; 05 Apr 2025 is the date of certifying given in paragraph 1.
  • Slab count: the description says 7 slabs laid by end of quarter, but the percentage column shows 3.
  • Council of Architects registration number and validity date fields are blank.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against RAHEJA DEVELOPERS LTD. (all its projects)320 (Complaint: 252; Compensation: 32; Execution of an earlier order: 36)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in