Projects · RAHEJA DEVELOPERS LTD.
Raheja Trinity
Raheja Developers · Sector 84, Gurugram
Registered with RERA: Jul 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jul 2022)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit its quarterly progress report; Authority issued show-cause notice (May 2022, open)
- Did not submit REP-I (Part A-H) project updates or update project webpage (Nov 2019, open). At stake: ₹25,000 per day imposed from 31 Dec 2019, capped at 5% of project cost
- 2 more cases: reply 4
- 3 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 2 refund ordered)
Will it be delivered on time?
- Deadline Dec 2022, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jan–Mar 2025):
- In progress: Excavation 76%, Raft foundation 69%, Basement level 2 49%, Walls on floors 36%, Basement level 1 33%, Stilt floor / ground floor 30%, and 8 more
- Money: ₹36.8 crore spent of ₹123.8 crore; ₹87 crore still to spend (CA certificate, Mar 2025)
Location
- Nearest metro: Millennium City Centre Gurugram, 18.9 km by road (49 min by car)
- Cyber City 56 min · Airport 40 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 0 malls
The builder: Raheja Developers
- 10 projects registered in Gurugram, 10 lapsed
- 0 with an occupation certificate on record
- 320 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | RAHEJA TRINITY |
|---|---|
| Builder (promoter) | RAHEJA DEVELOPERS LTD. |
| Location | SECTOR-84, GURUGRAM |
| RERA project ID | RERA-GRG-387-2019 |
| Registration certificate number | 24 OF 2017 DATED 25.07.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 25/07/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 2.281 acres |
| Licence | 26 of 2013 |
| Estimated cost of the project | ₹24,100 lakh (₹241 crore) |
| Total units (plots, apartments, shops) | 268 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 83 |
| Units unsold when registered | 185 |
| Layout plan approved on | 31-10-2013 |
| Building plans approved on | 31-10-2013 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 19-06-2019 |
|---|---|
| Revised completion date | 31-12-2022 |
| Infrastructure: projected completion | 31-12-2022 |
| Infrastructure: percentage complete when registered | 0% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2025 (JAN-MAR) |
| Latest report submitted on | 25-Apr-2025 |
| Quarterly reports listed on the portal | 26 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,361.93 lakh (₹13.62 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹2,312.53 lakh (₹23.13 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹2.96 lakh (₹0.03 crore) |
| Units in the project (apartments / plots) | 268 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹646.44 lakh (₹6.46 crore) paid; ₹1,331.57 lakh (₹13.32 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 05 Apr 2025, for 31 Mar 2025 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 3 |
|---|---|
| Cases |
|
| Decided cases against RAHEJA DEVELOPERS LTD. (all its projects) | 320 (Complaint: 252; Compensation: 32; Execution of an earlier order: 36) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in