Projects · RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD.
Rise
Ramprastha Promoters And Developers · Village Gadauli Kalan, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Dec 2023)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit quarterly progress report; show-cause notice issued (May 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2025, open). At stake: Penal proceedings would follow if builder fails to appear; no amount stated
- Did not file REP-I Part (A-H) form on HARERA website for project Rise, sector-44 (Nov 2019, open)
- 2 more cases: reply 4
- 16 complaints about this project decided by HRERA since Nov 2023 (15 delay interest ordered, 1 refund ordered)
Will it be delivered on time?
- Original deadline Dec 2023, extended to Dec 2023
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Money: ₹156.8 crore spent of ₹190.4 crore; ₹33.6 crore still to spend (CA certificate, Mar 2025)
What's on offer?
- 322 units: 317 sold, 5 unsold (builder's certificate, Mar 2025)
- Registration now covers 322 flats
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 3 BHK: 1,286–1,298 sq ft carpet, 314 units
The builder: Ramprastha Promoters & Developers
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 45 buyer complaints decided by HRERA
Share on WhatsApp
Full details and sources are below.
Registration
| Project name | RISE |
|---|
| Builder (promoter) | RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD. |
|---|
| Location | VILLAGE GADAULI KALAN |
|---|
| RERA project ID | RERA-GRG-447-2019 |
|---|
| Registration certificate number | 278 OF 2017 DATED 09.10.2017 |
|---|
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 31/12/2023 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 13998.08 acres |
|---|
| Licence | 33 of 2008(19-02-2008) |
|---|
| Estimated cost of the project | ₹18,732.28 lakh (₹187.32 crore) |
|---|
| Total units (plots, apartments, shops) | 322 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 3 BHK: 1,286–1,298 sq ft carpet, 314 units (source: the builder's registration form (Form A-H)) |
|---|
| Units booked when registered | 317 |
|---|
| Units unsold when registered | 5 |
|---|
| Layout plan approved on | 23-12-2011 |
|---|
| Building plans approved on | 12-04-2012 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-12-2020 |
|---|
| Revised completion date | 31-12-2023 |
|---|
| Infrastructure: projected completion | 31-12-2023 |
|---|
| Infrastructure: percentage complete when registered | 20% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/03/2025 (JAN-MAR) |
|---|
| Latest report submitted on | 21-Apr-2025 |
|---|
| Quarterly reports listed on the portal | 26 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹185 lakh (₹1.85 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹162.74 lakh (₹1.63 crore) |
|---|
| Spent on infrastructure in the quarter | ₹18.92 lakh (₹0.19 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹3 lakh (₹0.03 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0.32 lakh (₹0 crore) |
|---|
| Units in the project (apartments / plots) | 322 apartments |
|---|
| Sold in the quarter | 5 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 07-01-2011
- Zoning Plan: Obtained Approval 29-12-2008
- Service Plans: Obtained Approval 02-12-2014
- Electricity Plans: Obtained Approval 04-06-2020
- Site Plans: Obtained Approval 07-01-2011
- Building Plans: Obtained Approval 12-04-2012
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 07 Apr 2025, for 31 Mar 2025 |
|---|
| By part | - Tower A: Sub structure 100%; super structure 99%; mechanical MEP 1.95%; electrical MEP 39%; plumbing and firefighting 32%; internal finishing 38.50%; external finishing 39%
- Tower B: Sub structure 100%; super structure 99.10%; mechanical MEP 0.50%; electrical MEP 37%; plumbing and firefighting 47%; internal finishing 39.80%; external finishing 47.50%
- Tower C: Sub structure 100%; super structure 100%; mechanical MEP 0.50%; electrical MEP 44%; plumbing and firefighting 47.33%; internal finishing 39.70%; external finishing 38.50%
- Tower D: Sub structure 100%; super structure 100%; mechanical MEP 1.33%; electrical MEP 40.30%; plumbing and firefighting 34.90%; internal finishing 43.50%; external finishing 47.80%
|
|---|
| Unclear in the certificate | - The certificate gives a percentage for each component of each tower, but no single overall percentage per tower or for the whole project.
- For MEP and finishing, one work-done value and one cumulative value are shown for three or two sub-items together, so the value for each sub-item is not separately stated.
- The certificate does not state the percentage of work done during the quarter as one overall figure.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 5 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-2967-2022: A complaint case numbered RERA-GRG-2967-2022, listed as brought by HARERA Gurugram (through an official) against Ramprastha Promoters and Developers Pvt. Ltd. The document does not state the reason for the complaint. Status: The page shows the online complaint as not yet received at the office. The next date of hearing is NA, and the complaint dispatch fields are blank.
- RERA-GRG-3476-2022: The Authority issued a show cause notice to the promoter, Ramprastha Promoters and Developers Pvt. Ltd., for not submitting its quarterly progress report. Status: First hearing listed for 27 Jun 2022. The case page does not record what happened at that hearing or any order passed. Latest: 27 Jun 2022, First hearing was scheduled. The case page shows the status as 'First Hearing', with no proceedings, bench order or order uploaded.
- RERA-GRG-3699-2025: Suo motu case by the Authority against the promoter Ramprastha Promoters and Developers Pvt. Ltd. for violating section 4(2)(l)(C) of the Act by not completing the project within the declared time. The project is RISE, registration certificate no. 278 of 2017. Status: Pending. The Authority gave the promoter one more and final opportunity to appear and report project status, failing which penal proceedings would be initiated. The next hearing is fixed for 16 Jan 2026. Latest: 16 Jan 2026, Next hearing date listed. Status shown as pending.
- RERA-GRG-5215-2022: Case page for complaint RERA-GRG-5215-2022. The Authority (HARERA Gurugram) is shown as the first party against Rampprastha Promoters and Developers Pvt. Ltd. The page does not say what the complaint is about. Status: Listed at the first hearing stage. The first hearing was set for 30 Jun 2022. The page records no proceedings or order for that hearing. A document was received on 16 Jul 2022. Latest: 16 Jul 2022, A document was received under Dak ID 37876, recorded as NEW COMPLAINT. The page does not give its contents.
- RERA-GRG-5440-2019: The Authority started this proceeding against the promoter, Ramprastha Promoters and Developers Pvt. Ltd., for not filing the REP-I Part (A-H) form on the HARERA website for the registered project 'Rise' in sector-44, Gurugram. Status: Pending. The last listed hearing was 24 Feb 2020, and the page shows no order for that date. A third notice under Section 42 was dispatched on 16 Jul 2020. Latest: 16 Jul 2020, Third notice under Section 42 was dispatched to the promoter.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 16 |
|---|
| Cases | - RERA-GRG-4915-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4918-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4977-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4980-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4985-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4979-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4973-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4919-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4917-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4983-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4916-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4981-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4982-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4975-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4974-2024 (complaint, decided 12-Sep-2025): Buyers sought delayed possession interest; builder ordered to pay 10.85% p.a. interest from 30 Sep 2015 until possession.
- RERA-GRG-4061-2023 (complaint, decided 20-Mar-2024): Buyers sought refund after possession delay; builder ordered to refund Rs 74.39 lakh with 10.85% interest
|
|---|
| Decided cases against RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD. (all its projects) | 196 (Complaint: 153; Execution of an earlier order: 32; Compensation: 11) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in