Projects · AIPL BHARAT INFRASTRUCTURE PRIVATE LIMITED

Riviera At AIPL Lake City

AIPL Bharat Infrastructure · Sector 103, Gurugram

Registered with RERA: Dec 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: AIPL Bharat Infrastructure

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameRIVIERA AT AIPL LAKE CITY
Builder (promoter)AIPL BHARAT INFRASTRUCTURE PRIVATE LIMITED
LocationVILLAGE DAULTABAD SECTOR- 103
RERA project IDRERA-GRG-2085-2025
Registration certificate numberGGM/1019/751/2025/122 DATED 08.12.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/06/2033
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.1375 acres
Licence62 of 2025 Dated 01.05.2025
Estimated cost of the project₹98,725.52 lakh (₹987.26 crore)
Total units (plots, apartments, shops)412
Unit sizes (carpet area, as declared)7 units of 129 sq ft carpet; 61 units of 191 sq ft carpet; 6 units of 1,193 sq ft carpet; 86 units of 1,289 sq ft carpet; 3 units of 1,347 sq ft carpet; 45 units of 1,421 sq ft carpet; 35 units of 1,484 sq ft carpet; 83 units of 1,578 sq ft carpet; 3 units of 1,610 sq ft carpet; 83 units of 1,840 sq ft carpet
Flat types (BHK), as stated by the builder2 BHK; 3 BHK (source: the builder's floor plans uploaded to HRERA)
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on03-11-2025
Building plans approved on03-11-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2026
Likely completion date30-06-2033

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal3

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹4,115.31 lakh (₹41.15 crore)
Borrowed from banks / financial institutions in the quarter₹1,448.56 lakh (₹14.49 crore)
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,103.95 lakh (₹11.04 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,732.46 lakh (₹17.32 crore)
Project bank account (escrow): deposited in the quarter₹2,880.72 lakh (₹28.81 crore)
Project bank account (escrow): withdrawn in the quarter₹2,597 lakh (₹25.97 crore)
Project bank account (escrow): balance at quarter end₹339.18 lakh (₹3.39 crore)
Units in the project (apartments / plots)Not found in the records checked
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 01-05-2025
  • Service Plans: Obtained Approval 21-04-2026
  • Electricity Plans: Obtained Approval 28-04-2025
  • Site Plans: Obtained Approval 03-11-2025
  • Building Plans: Obtained Approval 03-11-2025
  • Fire NOC: Obtained Approval 12-02-2026

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 04 Oct 2026, for July to September 2026
By part
  • Sub structure (excavation, foundation, basements, water proofing): 7.15%, Work done value 114 in the quarter and 2007 cumulative till date, units not stated
  • Super structure (slabs, brick work, block work, staircase, lift wells, water tank): 0%, Not started
  • MEP: Mechanical (lifts, ventilation): 0%, Not started
  • MEP: Electrical (conduiting, wiring, fixtures): 0%, Not started
  • MEP: Plumbing and firefighting (piping, pumps, fixtures): 0%, Not started
  • Finishing: Internal (plaster, tiling, flooring, painting): 0%, Not started
  • Finishing: External (plaster, painting, facade): 0%, Not started
Unclear in the certificate
  • Table A values 114 (quarter) and 2007 (cumulative) have no unit stated.
  • Table A is filed for the whole project, with no tower-wise or building-wise split given.
  • Table B common areas and facilities are all marked Not Started, with no percentage figures.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against AIPL BHARAT INFRASTRUCTURE PRIVATE LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in