Projects · NANI RESORTS AND FLORICULTURE PVT. LTD.

ROF Aalayas Phase II

Nani Resorts And Floriculture · Sector 102, Gurugram

Registered with RERA: May 2019

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Nani Resorts And Floriculture

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameROF AALAYAS PHASE II
Builder (promoter)NANI RESORTS AND FLORICULTURE PVT. LTD.
LocationSECTOR-102, GURUGRAM
RERA project IDRERA-GRG-206-2019
Registration certificate numberGGM/339/71/2019/33 DATED 27.05.2019
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to02/07/2023
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area4.1125 acres
Licence82 of 2018 (05-12-2023)
Estimated cost of the project₹12,141.54 lakh (₹121.42 crore)
Total units (plots, apartments, shops)595
Unit sizes (carpet area, as declared)595 units averaging about 650 sq ft carpet (6 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on05-04-2019
Building plans approved on05-04-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction05-07-2019
Likely completion date05-07-2023

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on27-Jul-2026
Quarterly reports listed on the portal27

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹3.39 lakh (₹0.03 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)595 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹535.75 lakh (₹5.36 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 06-12-2018
  • Demarcation Plan: Obtained Approval 06-12-2018
  • Zoning Plan: Obtained Approval 07-12-2018
  • Service Plans: Obtained Approval 10-06-2019
  • Electricity Plans: Obtained Approval 12-06-2023
  • Site Plans: Obtained Approval 15-02-2019
  • Building Plans: Obtained Approval 27-05-2019
  • Fire NOC: Obtained Approval 23-05-2019

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Jun 2026, for 30 Jun 2026
By part
  • Building/Tower (name not filled in Table A): 100%, Occupation certificate received on 03 Jun 2024. All sub-structure, super-structure, MEP and finishing items shown at 100%.
  • Internal roads & pavements: 100%
  • Parking (covered 381 nos., open 582 nos.): 100%
  • Water supply: 100%
  • Sewerage (chamber, lines, septic tanks, STP): 100%
  • Storm water drains: 100%
  • Landscaping & tree plantation: 100%
  • Parks and playgrounds: 100%
  • Fixing of children play equipment: Nil
  • Benches: Nil
  • Street lighting/electrification: 100%
  • Fire protection and fire safety requirements: 100%
  • Solid waste management & disposal: Nil
  • Water conservation, rain water harvesting, percolating well/pit: Nil
Unclear in the certificate
  • Table A is headed 'Building/Tower no.' but no tower or building name is written in it.
  • Table A and Table B do not state a 'work done during the quarter' figure, so only cumulative percentages are reported.
  • Shopping area, sewage treatment (STP), solar energy and electrical sub-station are marked NO or NA in Table B and are not counted.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusScrutinized: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project6
Cases
Decided cases against NANI RESORTS AND FLORICULTURE PVT. LTD. (all its projects)17 (Complaint: 15; Execution of an earlier order: 1; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in