Projects · PEGASUS LAND AND HOUSING PRIVATE LIMITED
ROF Ambliss
Pegasus Land And Housing · Sector 78, Gurugram
Registered with RERA: Aug 2022
Is it legal?
- RERA registered, valid till Apr 2027
- HRERA opened a case of its own against the builder in Nov 2022 (still open):
- Why: did not submit service estimates and plans, fire scheme approval, tree-cutting permission by 30 Oct 2022
- Latest: second notice dispatched 16 Jan 2026; next hearing listed for same date
- At stake: show-cause notice warned of bank guarantee forfeiture and registration revocation; no penalty imposed
Will it be delivered on time?
- Deadline May 2027, never extended
- No occupation certificate yet (not ready for possession)
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 3 BHK
- 798 units in 4 sizes, as declared to HRERA:
- 108 units of 493 sq ft carpet (2 towers)
- 108 units of 504 sq ft carpet (2 towers)
- 292 units of 643 sq ft carpet (5 towers)
- 290 units of 645 sq ft carpet (5 towers)
Location
- Nearest metro: Millennium City Centre Gurugram, 20.6 km by road (48 min by car)
- Cyber City 55 min · Airport 45 min by car at 9:30 am
- Within 3 km: 1 hospital, 0 schools, 0 malls
The builder: Pegasus Land And Housing
- 2 projects registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ROF AMBLISS |
|---|---|
| Builder (promoter) | PEGASUS LAND AND HOUSING PRIVATE LIMITED |
| Location | VILLAGE-SHIKOHPUR, SECTOR-78 |
| RERA project ID | RERA-GRG-1094-2022 |
| Registration certificate number | GGM/599/331/2022/74 DATED 01.08.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 12/04/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.375 acres |
| Licence | 58 OF 2022 DATED 13.05.2022 |
| Estimated cost of the project | ₹17,000 lakh (₹170 crore) |
| Total units (plots, apartments, shops) | 798 |
| Unit sizes (carpet area, as declared) | 108 units of 493 sq ft carpet (2 towers); 108 units of 504 sq ft carpet (2 towers); 292 units of 643 sq ft carpet (5 towers); 290 units of 645 sq ft carpet (5 towers) |
| Flat types (BHK), as stated by the builder | 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-08-2022 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-08-2022 |
|---|---|
| Likely completion date | 12-05-2027 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 02-Nov-2026 |
| Quarterly reports listed on the portal | 16 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹73.12 lakh (₹0.73 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹373.74 lakh (₹3.74 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹853.91 lakh (₹8.54 crore) |
| Project bank account (escrow): deposited in the quarter | ₹51.18 lakh (₹0.51 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹60.5 lakh (₹0.61 crore) |
| Project bank account (escrow): balance at quarter end | ₹0.3 lakh (₹0 crore) |
| Units in the project (apartments / plots) | 798 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹826.2 lakh (₹8.26 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|---|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against PEGASUS LAND AND HOUSING PRIVATE LIMITED (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in