Projects · PARDOS CRAFT HOMES PVT. LTD.
Sakura
Pardos Craft Homes · Sector 90, Gurugram
Registered with RERA: Nov 2026
Is it legal?
- RERA registered, valid till May 2034
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline May 2034, never extended
- No occupation certificate yet (not ready for possession)
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
- 2 BHK + store
- 3 BHK
- 998 units, as declared to HRERA:
- 136 units averaging about 190 sq ft carpet (1 tower)
- 101 units averaging about 1,120 sq ft carpet (1 tower)
- 761 units averaging about 1,440 sq ft carpet (9 towers)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units.
Location
- Nearest metro: Millennium City Centre Gurugram, 20.4 km by road (52 min by car)
- Cyber City 59 min · Airport 43 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Pardos Craft Homes
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SAKURA |
|---|---|
| Builder (promoter) | PARDOS CRAFT HOMES PVT. LTD. |
| Location | VILLAGE - HAYATPUR, SECTOR - 90, GURUGRAM |
| RERA project ID | RERA-GRG-2307-2026 |
| Registration certificate number | GGM/1095/827/2026/67 DATED 02.11.2026 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 13/05/2034 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 14.53125 acres |
| Licence | 100 of 2023 dated 08-05-2023 |
| Estimated cost of the project | ₹2,09,948.7 lakh (₹2,099.49 crore) |
| Total units (plots, apartments, shops) | 998 |
| Unit sizes (carpet area, as declared) | 136 units averaging about 190 sq ft carpet (1 tower); 101 units averaging about 1,120 sq ft carpet (1 tower); 761 units averaging about 1,440 sq ft carpet (9 towers) |
| Flat types (BHK), as stated by the builder | 2 BHK; 2 BHK + store; 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 14-05-2025 |
| Building plans approved on | 14-05-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-07-2026 |
|---|---|
| Likely completion date | 13-05-2034 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | NA |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against PARDOS CRAFT HOMES PVT. LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in