RERA’d by NeevHQ

Projects · SANTUR REALTORS PVT. LTD.

Santur Aspira

Santur Realtors · Sector 3, Gurugram

Registered with RERA: Apr 2019

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Santur Realtors

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSANTUR ASPIRA
Builder (promoter)SANTUR REALTORS PVT. LTD.
LocationSECTOR-3, GURUGRAM
RERA project IDRERA-GRG-148-2019
Registration certificate numberGGM/323/55/2019/17 DATED 01.04.2019
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/11/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area2.5625 acres
Licence50 of 2014
Estimated cost of the project₹6,831.57 lakh (₹68.32 crore)
Total units (plots, apartments, shops)141
Unit sizes (carpet area, as declared)3 units of 389 sq ft carpet; 4 units of 1,162 sq ft carpet (1 tower); 20 units of 1,163 sq ft carpet (3 towers); 52 units of 1,164 sq ft carpet; 16 units of 1,166 sq ft carpet (3 towers); 10 units of 1,209 sq ft carpet (1 tower); 30 units of 1,211 sq ft carpet (3 towers); 2 units of 2,311 sq ft carpet (1 tower); 2 units of 2,333 sq ft carpet (1 tower); 2 units of 2,339 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on17-01-2018
Building plans approved on17-01-2018

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2017
Likely completion date31-05-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2024 (JUL-SEP)
Latest report submitted on26-Oct-2024
Quarterly reports listed on the portal21

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2024 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,043.22 lakh (₹10.43 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹130.53 lakh (₹1.31 crore)
Spent on infrastructure in the quarter₹0.26 lakh (₹0 crore)
Other costs in the quarter (EDC, taxes, etc.)₹64.06 lakh (₹0.64 crore)
Project bank account (escrow): deposited in the quarter₹730.25 lakh (₹7.3 crore)
Project bank account (escrow): withdrawn in the quarter₹749.4 lakh (₹7.49 crore)
Project bank account (escrow): balance at quarter end₹1.08 lakh (₹0.01 crore)
Units in the project (apartments / plots)138 apartments
Sold in the quarter14 apartments
EDC (development charges): paid / due as on date₹991.64 lakh (₹9.92 crore) paid; ₹991.64 lakh (₹9.92 crore) due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 05 Oct 2024
By part
  • Excavation: 100%
  • One number of Basement(s) and Plinth: 100%
  • Stilt Floor: 100%
  • 36 number of Slabs of Super Structure: 100%
  • Internal walls, internal plaster, flooring, doors and windows in each flat/premises: 100%
  • Sanitary and electrical fittings within the flat/premises: 90%
  • Staircases, lift wells and lobbies at each floor, overhead and underground water tanks: 100%
  • External plumbing, external plaster, elevation, and terraces with waterproofing of the building/block/tower: 100%
  • Installation of lifts, water pumps, fire fighting equipment, electrical fittings to common areas, and other items needed for Occupation/Completion Certificate: 100%
  • Internal Roads & Footpaths: 100%
  • Water Supply: 100%
  • Sewerage (chamber, lines, septic tank, STP): 100%
  • Storm Water Drains: 100%
  • Landscaping & Tree Planting: 95%
  • Street Lighting: 100%
  • Community Buildings (one EWS block having 24 units): 100%
  • Treatment and disposal of sewage and sullage water: 100%
  • Solid Waste management & Disposal: 100%
  • Water conservation, rain water harvesting: 100%
  • Fire protection and fire safety requirements: 100%
  • Electrical meter room, sub-station, receiving station: 100%
  • Other (Guard Room/Main Gate): 100%

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusScrutinized: 1; First Hearing: 4; Online Complaint Not Yet Received At Office: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SANTUR REALTORS PVT. LTD. (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in