Projects · CROWN PROPBUILD PVT.LTD

Sapphire Ninety

Crown Propbuild · Sector 90, Gurugram

Registered with RERA: Jan 2018

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 90; the exact site was not found.

The builder: Crown Propbuild

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSAPPHIRE NINETY
Builder (promoter)CROWN PROPBUILD PVT.LTD
LocationSECTOR-90, VILLAGE NAWADA FAT EHPUR
RERA project IDRERA-GRG-339-2019
Registration certificate number05 OF 2018 DATED 01.01.2018
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/06/2020
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area3.840625 acres
Licence.53 of 2013 dated 28.06.2013 Renewed on 08.11.2017 Renewed on 10.09.2019
Estimated cost of the project₹21,000 lakh (₹210 crore)
Total units (plots, apartments, shops)327
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered145
Units unsold when registered182
Layout plan approved on10-03-2017
Building plans approved on10-03-2017

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-06-2020
Revised completion date30-06-2020
Infrastructure: projected completion30-06-2020
Infrastructure: percentage complete when registered100%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2024 (APR-JUN)
Latest report submitted on15-Jul-2024
Quarterly reports listed on the portal23

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2024 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹84.87 lakh (₹0.85 crore)
Project bank account (escrow): deposited in the quarter₹375.81 lakh (₹3.76 crore)
Project bank account (escrow): withdrawn in the quarter₹607.55 lakh (₹6.08 crore)
Project bank account (escrow): balance at quarter end₹13.06 lakh (₹0.13 crore)
Units in the project (apartments / plots)345 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹1,427.63 lakh (₹14.28 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 23-01-2014
  • Demarcation Plan: Obtained Approval 28-06-2013
  • Zoning Plan: Obtained Approval 28-06-2013
  • Service Plans: Obtained Approval 10-09-2019
  • Electricity Plans: Obtained Approval 17-05-2019
  • Site Plans: Obtained Approval 23-01-2014
  • Building Plans: Obtained Approval 18-09-2019
  • Fire NOC: Obtained Approval 28-06-2013

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 03 Mar 2020, for 13 Dec 2019
By part
  • Sapphire Ninety (Table A, single tower/building entry): 100%, Table A shows every listed component (sub-structure, super-structure, MEP, internal and external finishing) at 100% of proposed work. Basements 1 and 2 complete. Building is G+15 floors. Lifts, overhead and underground tanks, electrical fittings and compound wall shown complete. Table B common amenities shown at 100% where applicable; internal roads, parks and some community buildings marked not applicable.
Unclear in the certificate
  • The certificate does not give one overall percentage of construction complete; only component-wise 100% figures are shown.
  • Table A gives work done in the quarter as 489.65 Lacs and cumulative work value as 9906.64 Lacs, not as percentages, so they are not used in the percentage fields.
  • Parts of the scanned text are garbled, including some Table B parking figures and the architect's signature block, so some entries may be misread.
  • Table A is titled for a single building/tower 'Sapphire Ninety' and the document does not name separate towers.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusFirst Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against CROWN PROPBUILD PVT.LTD (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026