Projects · VATIKA SEVEN ELEMENTS PVT. LTD.
Seven Elements
Vatika Seven Elements · Sector 89, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till Jan 2030
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit a quarterly progress report (open)
- Failed to extend expired registration; no completion or occupation certificate submitted; required documents not submitted (Jun 2022, open)
- Did not complete the project within the time it declared (Jun 2022, open)
- 3 more cases: reply 4
- 10 complaints about this project decided by HRERA since Nov 2023 (4 delay interest ordered, 4 refund ordered, 2 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline Jan 2022, extended 2 times to Jan 2030
- The order keeps buyers' right to a refund or interest for the delay
- Occupation certificate (Aug 2026) covers: Blocks B1-B4, Towers A2-A4, EWS, community building, shops (470 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Phase i - external finishing 94.29%, Phase i - sub structure 92.99%, Phase i - electrical 72.77%, Phase i - plumbing and firefighting 56.12%, Phase i - mechanical 45.18%, Phase i - internal finishing 42.5%
- Money: ₹762.6 crore spent of ₹828.6 crore; ₹66 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 589 units: 380 sold, 209 unsold (builder's certificate, Sep 2026)
- Apartment: 380 of 589 sold
- Registration now covers 580 units and 10 retail shops
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
Location
- Nearest metro: Millennium City Centre Gurugram, 20 km by road (52 min by car)
- Cyber City 58 min · Airport 41 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Vatika Seven Elements
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 21 buyer complaints decided by HRERA
★ Vatika Seven Elements was earlier called Strong Infrabuild Pvt. Ltd. Its history under the earlier name matters too: 0 projects, 0 decided buyer complaints.
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SEVEN ELEMENTS |
|---|
| Builder (promoter) | VATIKA SEVEN ELEMENTS PVT. LTD. |
|---|
| Location | SECTOR 89-A, VILLAGE HARSARU AND HAYATPUR, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-460-2019 |
|---|
| Registration certificate number | 281 OF 2017 DATED 09.10.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/01/2030 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 57870.05 acres |
|---|
| Licence | 41 of 2013 Dated 06.06.2013 |
|---|
| Estimated cost of the project | ₹81,536 lakh (₹815.36 crore) |
|---|
| Total units (plots, apartments, shops) | 589 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 3 BHK (source: the builder's floor plans uploaded to HRERA) |
|---|
| Units booked when registered | 116 |
|---|
| Units unsold when registered | 473 |
|---|
| Layout plan approved on | 17-10-2014 |
|---|
| Building plans approved on | 17-10-2014 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-01-2022 |
|---|
| Revised completion date | 31-01-2022 |
|---|
| Infrastructure: projected completion | 31-01-2022 |
|---|
| Infrastructure: percentage complete when registered | 29% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 02-Nov-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹8,200.23 lakh (₹82 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹26,682.45 lakh (₹266.82 crore) |
|---|
| Spent on infrastructure in the quarter | ₹968.56 lakh (₹9.69 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹34,368.57 lakh (₹343.69 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹5,810.16 lakh (₹58.1 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹5,376.3 lakh (₹53.76 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹830.81 lakh (₹8.31 crore) |
|---|
| Units in the project (apartments / plots) | 589 apartments |
|---|
| Sold in the quarter | 5 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹3,994.97 lakh (₹39.95 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 01-04-2013
- Zoning Plan: Obtained Approval 06-06-2013
- Service Plans: Obtained Approval 16-10-2015
- Electricity Plans: Obtained Approval 01-10-2014
- Site Plans: Obtained Approval 17-10-2014
- Building Plans: Obtained Approval 17-10-2014
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|
| By part | - Phase I - Sub structure (excavation, foundation, basements, waterproofing): 92.99%, Table A shows 92.99% against a merged cell covering sub and super structure. Basement levels 1 and 2 RCC work 100% complete; raft RCC work 100%.
- Phase I - Super structure: Slabs cast 92% of cumulative number laid by end of quarter; walls on floors (block work) 83%; staircase 75.4%; lift wells with waterproofing 74.5%; lift lobbies and common areas 76%; fixing of door and window frames in flats 26%.
- Phase I - Mechanical (lifts, ventilation): 45.18%
- Phase I - Electrical (conducting, wiring, fixtures): 72.77%, Slab and wall conduiting
- Phase I - Plumbing and firefighting (piping, pumps, fixtures): 56.12%
- Phase I - Internal finishing (plaster, tiling, flooring, painting within units and common areas): 42.5%, Internal plaster (gypsum) 42.50%; wall tiling in bathrooms 54% and kitchens 53%; flooring in common areas 46% and in units 52%
- Phase I - External finishing (plaster, painting, facade): 94.29%, External cement plaster; external walls white washing 62%
- Phase I - Other works: Waterproofing of terraces 88%; entrance lobby finishing 48%; compound wall (RCC and brick) 88%; overhead tanks 100%; underground water tank RCC work done; staircase with railing 67%; lift wells finishing 49%; lift installation 58%; fire fitting and equipment as per CFO NOC 53%
|
|---|
| Unclear in the certificate | - The certificate does not name the tower or building. Table A is headed 'Building/Tower no.' with only 'Phase I' written.
- The 92.99% sub structure figure in Table A sits in a cell shared with the super structure row, so it is not clear which row it applies to.
- No single overall percentage of completion for the whole project is stated.
- No percentage of work done during the quarter is stated as one figure; Table A gives rupee values for work done during the quarter instead.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate dated 31 Aug 2026: covers Occupation permission for Blocks B1 to B3 (Type-A), Block B4 (Type-1B), Towers A2 to A4, the EWS building, the community building under Tower A4, and the community building and convenient shopping area. These form part of a Group Housing Colony on 14.30 acres (Licence No. 41 of 2013) in Sector 89A, Gurugram. Tower-wise: Blocks B1 to B4 have 32 units each (128 total, Ground Floor to 8th Floor). Tower A2 has 77 units, Tower A3 has 77 units and Tower A4 has 74 units (all Ground Floor to 20th Floor). The EWS building has 114 units (Ground Floor to 6th Floor). The community building and convenient shopping are on the ground floor only. Basements and stilt are to be used as per the approved plans.. Addressed to Vatika Seven Elements Pvt. Ltd. (formerly Strong Infrabuild Pvt. Ltd.) and others. Composition fees for variations from approved plans: ₹15,39,990
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 281 of 2017 / 7(3) / 39 / 2023 / 16 dated 24 Nov 2023: registration extended from 31 Mar 2021, plus six months COVID-19 extension to 30 Sep 2021 to 31 Jan 2026. Conditions include: The apartments are to be sold on a carpet area basis, and the total sale consideration includes all charges. No separate EDC/IDC is payable beyond the total sale consideration.; The permission is without prejudice to the allottees' right to delay possession charges under section 18(1) of the Act, and the promoter must pay such charges from its own funds.; The promoter must not accept more than ten percent of the cost as advance or application fee without first signing a written agreement for sale.; A penalty of Rs. 25 lakhs was imposed for violation of sections 3 and 4 of the Act, to be deposited before this certificate is issued.; The promoter declared 31 Jul 2026 as the completion date for the entire project, and some licences and approvals were to expire before then. The promoter must renew approvals on time.; Dates of possession already set in signed agreements for sale will not change if they fall before the date in the detailed project information.; The promoter must file quarterly progress reports. Failure may lead to withdrawal of the permission or revocation of registration.; Community sites must be completed within the declared completion period, and the promoter must get accounts audited within six months after each financial year.; The promoter must enable formation of an association of allottees within three months after a majority of allottees have booked.; The promoter must not create any further encumbrance on future receivables from unsold units or RERA accounts, except the charge already created in favour of SWAMIH Fund.
- Extension Continuation No. 16 of 2023 dated 10 Apr 2026: registration extended from 31 Jan 2026 to 30 Jan 2030. Conditions include: The permission is without prejudice to allottees' rights under section 18(1) on delay possession charges from the due date of possession until actual handing over.; The promoter must pay delay possession charges to allottees from its own funds. Project cash inflow must not be used for this.; The promoter must deposit 100% of amounts realised from allottees in a separate account in a schedule bank, to be used only for construction and proportionate land cost.; The promoter must offer to execute and register a conveyance deed in favour of the allottee or association, as per section 17.; The promoter must not accept more than 10% of the unit cost as advance payment without a written agreement for sale, as per section 13(1).; Individual possession dates in already executed agreements for sale will not be changed if they are earlier than the possession date in the detailed project information.; The apartment is to be sold on a carpet area basis, and the total price includes all charges with no separate EDC/IDC payable.; An association of allottees must be formed within three months of the majority of allottees having booked, as per section 11(4)(e).; No subvention or assured return scheme is allowed without prior approval of the Authority.; The promoter has deposited a Rs 25 lakh penalty (RTGS dated 18 Mar 2026) for violation of section 4(2)(l)(c) before this certificate was issued.; The promoter must submit quarterly up-to-date project status and a monthly comparison of proposed and actual work on the 7th day of each month.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2972-2022: Case RERA-GRG-2972-2022 listed as Haryana Real Estate Regulatory Authority (Gurugram) versus Vatika Seven Elements Pvt. Ltd. The page does not say what the case is about. Status: The page shows 'Online complaint not yet received at office'. No next hearing date is listed, and the complaint is marked as not yet dispatched.
- RERA-GRG-3479-2022: Show cause notice by the Authority to the promoter for not submitting a quarterly progress report Status: First hearing listed for 27 Jun 2022. The case page shows no proceedings or order yet. Latest: 27 Jun 2022, First hearing listed. Status shown as first hearing with no proceedings or order recorded.
- RERA-GRG-3722-2022: Show cause notice to the promoter, Vatika Seven Elements Pvt. Ltd., for not applying to extend its registration, which had expired, and for not submitting a completion, part completion or occupation certificate, and other required documents. Status: First hearing listed for 28 Jun 2022. No proceedings or order recorded yet. Latest: 28 Jun 2022, First hearing listed. Status shows 'First Hearing', with no proceedings of the day, bench order or order uploaded.
- RERA-GRG-3724-2022: Show-cause notice to the promoter Vatika Seven Elements Pvt. Ltd. for not completing the project within the time it declared, under section 4(2)(l)(C) of the RERA Act. The Authority started this case itself. Status: First hearing listed for 30 Jun 2022. No proceedings, bench order or order was recorded on the page as of the page date. Latest: 30 Jun 2022, First hearing was listed. The status shows 'First Hearing' with no proceedings, bench order or order uploaded.
- RERA-GRG-5218-2022: Case titled HARERA Gurugram through a representative versus Vatika Seven Elements Pvt. Ltd. The case page does not state the subject matter of the complaint. Status: Listed for first hearing on 30 Jun 2022. The page shows no proceedings, order or later hearing date. Latest: 16 Jul 2022, Documents submitted on the complainant side under Dak ID 37873, with the remark 'NEW COMPLAINT'.
- RERA-GRG-5443-2019: The Authority's own proceeding against Vatika Seven Elements Pvt. Ltd. about filing the REP-I Part (A-H) details on the HARERA website for the registered project Seven Elements (Phase-1), and compliance with notices under Section 42 and the QPR requirement. Status: Pending as per the case page. The last hearing shown is 24 Feb 2020 with no proceedings recorded for it. A third notice was dispatched on 03 Sep 2020 and the case page shows the complaint dispatched that day. Latest: 03 Sep 2020, Third notice dispatched to the promoter for compliance of Section 42 (A-H) and QPR. The complaint was also dispatched on this date.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 10 |
|---|
| Cases | - RERA-GRG-3996-2025 (complaint, decided 13-Jan-2026): Buyer sought possession and delay interest; builder ordered to pay 10.80% interest on paid amount and hand over after OC.
- RERA-GRG-3998-2025 (complaint, decided 13-Jan-2026): Buyer sought possession and delay interest after 2020 due date; builder ordered to pay 10.80% interest on paid amount
- RERA-GRG-3999-2025 (complaint, decided 13-Jan-2026): Buyer sought possession and delay interest; builder ordered to pay 10.80% interest on paid amount.
- RERA-GRG-5393-2024 (execution of an earlier order, decided 24-Nov-2025): Buyer and builder settled the dispute; complaint disposed of as per settlement deed.
- RERA-GRG-8044-2022 (complaint, decided 17-Oct-2025): Buyers sought refund after an inordinate delay in possession; builder ordered to refund Rs 25.5 lakh with 10.85% interest.
- RERA-GRG-2706-2024 (complaint, decided 11-Jul-2025): Buyer sought refund of Rs 8 lakh token amount; HRERA dismissed the complaint as filed too late, and the amount stood forfeited.
- RERA-GRG-2370-2024 (complaint, decided 02-Jul-2025): Buyers sought refund after possession delay; builder ordered to refund Rs 1.37 crore with 11.10% interest.
- RERA-GRG-1347-2024 (complaint, decided 22-May-2025): Buyer sought refund after possession delay with no occupancy certificate; builder ordered to refund Rs 66.89 lakh with 11.10% interest
- RERA-GRG-4468-2023 (complaint, decided 22-Nov-2024): Buyer sought possession with delay interest after possession was due 21 Nov 2018; builder ordered to pay 11.10% interest and offer possession.
- RERA-GRG-3747-2020 (complaint, decided 07-Nov-2024): Buyers sought refund after withdrawing from project; HRERA ordered builder to refund Rs 33.63 lakh less 10% with 11.10% interest.
|
|---|
| Decided cases against VATIKA SEVEN ELEMENTS PVT. LTD. (all its projects) | 21 (Complaint: 16; Compensation: 3; Execution of an earlier order: 2) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in