Projects · ARMY WELFARE HOUSING ORGANISATION
Shanti Vihar ( Tower A To R)
Army Welfare Housing Organisation · Sector 95, Gurugram
Registered with RERA: Jan 2018
Is it legal?
- RERA registered, valid till Dec 2020 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit its quarterly progress report (open)
- Did not apply to extend registration, file completion or occupation certificate, or submit requisite documents (Jun 2022, open)
- Did not complete Shanti Vihar project within the time it declared (Jun 2022, open)
- 2 more cases: reply 4
- 2 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 1 refund ordered)
Will it be delivered on time?
- Deadline Dec 2021, never extended (date has passed)
- Occupation certificate (Oct 2020) covers: Towers A to R, EWS block, shops, community building
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 2 BHK: 162 units
- 2 BHK + study: 300 units
- 3 BHK: 539 units
- 4 BHK: 220 units
Location
- Nearest metro: Millennium City Centre Gurugram, 22.6 km by road (55 min by car)
- Cyber City 62 min · Airport 45 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Army Welfare Housing Organisation
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 4 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SHANTI VIHAR ( TOWER A TO R) |
|---|---|
| Builder (promoter) | ARMY WELFARE HOUSING ORGANISATION |
| Location | SECTOR-95, WAZIRPUR |
| RERA project ID | RERA-GRG-395-2019 |
| Registration certificate number | 08 OF 2018 DATED 04.01.2018 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2020 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 24.53 acres |
| Licence | 40 of 2010(28 .05 .2010) |
| Estimated cost of the project | ₹8,24,73,13,650 lakh (₹8,24,73,136.5 crore) |
| Total units (plots, apartments, shops) | 1221 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK: 162 units; 2 BHK + study: 300 units; 3 BHK: 539 units; 4 BHK: 220 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 1167 |
| Units unsold when registered | 54 |
| Layout plan approved on | 20-04-2012 |
| Building plans approved on | 20-04-2012 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-12-2015 |
|---|---|
| Revised completion date | 31-12-2021 |
| Infrastructure: projected completion | 31-12-2020 |
| Infrastructure: percentage complete when registered | 90% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 2 |
|---|---|
| Cases |
|
| Decided cases against ARMY WELFARE HOUSING ORGANISATION (all its projects) | 4 (Complaint: 4) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026