Shf Homes
Shf Square · Sector 3, Gurugram
Registered with RERA: Feb 2022
Is it legal?
- RERA registered, valid till Mar 2023 (date has passed)
- HRERA opened a case of its own against the builder in Jul 2024 (still open):
- Why: allegedly let registration certificate expire; builder says it applied for completion certificate in time
- Latest: order uploaded 27 Aug 2024 after first hearing on 09 Aug 2024
- 1 complaint about this project decided by HRERA since Nov 2023 (1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Mar 2023, never extended (date has passed)
- Occupation certificate (Jul 2023) covers: Affordable plotted colony, Sector-3, Farukhnagar (7.01875 acres)
- Money: ₹31 crore spent of ₹26.8 crore (CA certificate, Sep 2023)
What's on offer?
- 129 plots, 112–173 sq yd
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 31.9 km by road (46 min by car)
- Cyber City 81 min · Airport 63 min by car at 9:30 am
- Within 3 km: 8 hospitals, 0 schools, 0 malls
The builder: Shf Square
- 2 projects registered in Gurugram, 1 lapsed
- 1 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SHF HOMES |
|---|---|
| Builder (promoter) | SHF SQUARE LLP |
| Location | SHF HOMES, SECTOR 3, FARUKHNA GAR, DISTRICT - --GURGAON |
| RERA project ID | RERA-GRG-975-2021 |
| Registration certificate number | GGM/541/273/2022/16 DATED 28.02.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/03/2023 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 7.01875 acres |
| Licence | 49 OF 2017 dated 16.07.2017 |
| Estimated cost of the project | ₹2,682.81 lakh (₹26.83 crore) |
| Total units (plots, apartments, shops) | 129 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-10-2021 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-10-2021 |
|---|---|
| Likely completion date | 31-03-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2023 (JUL-SEP) |
| Latest report submitted on | 17-Oct-2023 |
| Quarterly reports listed on the portal | 6 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2023 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹885.57 lakh (₹8.86 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹16 lakh (₹0.16 crore) |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹160.69 lakh (₹1.61 crore) |
| Project bank account (escrow): deposited in the quarter | ₹616.28 lakh (₹6.16 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹689.47 lakh (₹6.89 crore) |
| Project bank account (escrow): balance at quarter end | ₹15.53 lakh (₹0.16 crore) |
| Units in the project (apartments / plots) | 129 plots |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹35.44 lakh (₹0.35 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 11 Oct 2023, for July – September 2023 |
|---|---|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | First Hearing: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against SHF SQUARE LLP (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in