Projects · SHREE VARDHMAN INFRAHOME PVT. LTD
Shree Vardhman Flora
Shree Vardhman Infrahome · Sector 90, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jun 2019)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not file REP-I (Part A to H) form on Authority's web portal for offline registered project (Jun 2022, open)
- Did not apply to extend registration; did not submit completion or occupation certificate (Jun 2022, open)
- Allegedly did not complete Shree Vardhman Flora within declared time; missed hearings (Jun 2022, open). At stake: Penal proceedings may be initiated if builder fails to appear; no penalty imposed yet
- 4 more cases: reply 4
- 14 complaints about this project decided by HRERA since Nov 2023 (13 delay interest ordered, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Dec 2020, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Money: ₹261.8 crore spent of ₹264.1 crore; ₹2.3 crore still to spend (CA certificate, Mar 2025)
What's on offer?
- 573 units: 436 sold, 137 unsold (builder's certificate, Mar 2025)
- Apartments: 436 of 573 sold
- Shops: ? of 12 sold
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 2 BHK: 235 units
- 3 BHK: 279 units
- 4 BHK: 59 units
Location
- Nearest metro: Millennium City Centre Gurugram, 21.5 km by road (56 min by car)
- Cyber City 63 min · Airport 48 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Shree Vardhman Infrahome
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 90 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SHREE VARDHMAN FLORA |
|---|
| Builder (promoter) | SHREE VARDHMAN INFRAHOME PVT. LTD |
|---|
| Location | SECTOR 90, HAYATPUR, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-727-2020 |
|---|
| Registration certificate number | 88 OF 2017 DATED 23.08.2017 |
|---|
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/06/2019 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 10.881 acres |
|---|
| Licence | 23 of 2008 dated 11th February, 2008 |
|---|
| Estimated cost of the project | ₹18,972.9 lakh (₹189.73 crore) |
|---|
| Total units (plots, apartments, shops) | 573 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 2 BHK: 235 units; 3 BHK: 279 units; 4 BHK: 59 units (source: the builder's registration form (Form A-H)) |
|---|
| Units booked when registered | 425 |
|---|
| Units unsold when registered | 148 |
|---|
| Layout plan approved on | 16-12-2011 |
|---|
| Building plans approved on | 16-12-2011 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2019 |
|---|
| Revised completion date | 31-12-2020 |
|---|
| Infrastructure: projected completion | 31-12-2020 |
|---|
| Infrastructure: percentage complete when registered | 0% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/03/2025 (JAN-MAR) |
|---|
| Latest report submitted on | 16-Jul-2025 |
|---|
| Quarterly reports listed on the portal | 26 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹150.11 lakh (₹1.5 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹-70 lakh (₹-0.7 crore) |
|---|
| Put in by the builder in the quarter | ₹32.57 lakh (₹0.33 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹-58.74 lakh (₹-0.59 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹-143.58 lakh (₹-1.44 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹263.49 lakh (₹2.63 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹-202.32 lakh (₹-2.02 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹206.95 lakh (₹2.07 crore) |
|---|
| Units in the project (apartments / plots) | 573 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
|---|
| Approvals listed | Not found in the records checked |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | for 31 Mar 2025 |
|---|
| By part | - 573 apartments and 12 shops: Completed, OC obtained, possession is in process
|
|---|
| Unclear in the certificate | - The certificate gives no percentage of work complete, overall or for the quarter.
- The certificate has no date of signing.
- The heading 'Plot/Floors Details' is struck through in the document.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | - Rejection order and Form intimation for rejection of application for extension of registration of real estate project (Shree Vardhman Flora, Sector 90, Gurugram); not a corrigendum or addendum dated 10 Feb 2020: The Authority rejected the promoter's application for extension of registration of the project Shree Vardhman Flora, Sector 90, Gurugram, filed on 26 Jun 2019. The registration certificate No. 88 of 2017 dated 23 Aug 2017 had a validity up to 30 Jun 2019. The reasons were that the promoter did not remove deficiencies: the licence validity expired on 10 Feb 2018 and was not renewed, AAI renewal was not provided, copies of service plans and estimates were not provided, and fees of Rs 1,585,617 were not deposited. The promoter was given notices and hearings on 06 Aug 2019, 20 Aug 2019, 19 Sep 2019 (as recorded), and 10 Feb 2020 but did not rectify the deficiencies. A show cause notice was dated 08 Jan 2020.
|
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | First Hearing: 4; Online Complaint Not Yet Received At Office: 1; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-2643-2022: The Authority started this proceeding against the promoter, Shree Vardhman Infrahome Pvt. Ltd, for not filing the REP-I (Part A to H) form on the Authority's web portal for an offline registered project. The filing was required with either the Interim Real Estate Regulatory Authority, Panchkula, or the Haryana Real Estate Regulatory Authority, Gurugram. Status: The case is at the first hearing stage. The first hearing was listed for 29 Jun 2022 at 11:00 am before the Authority in Gurugram. The listing shows the status as FIRST HEARING, with no proceedings or order recorded. Latest: 29 Jun 2022, First hearing was listed before the Authority at 11:00 am in Gurugram. The promoter was asked to appear if it had anything to say in the matter. No proceedings or order are recorded on the case page.
- RERA-GRG-2721-2022: Case RERA-GRG-2721-2022 is listed with HARERA Gurugram as the party against Shree Vardhman Infrahome Pvt. Ltd. The page does not state what the case is about. Status: The page shows the online complaint has not yet been received at the office. No next hearing date is set.
- RERA-GRG-2912-2022: The Authority issued a show cause notice to the promoter, Shree Vardhman Infrahome Pvt. Ltd, for not applying to extend its real estate registration, and for not submitting a completion certificate, part completion certificate or occupation certificate, and other required documents. The registration is shown as expired. Status: First hearing listed for 28 Jun 2022. The case listing shows status 'First Hearing', with no proceedings, bench order or order uploaded. Latest: 28 Jun 2022, First hearing scheduled. The listing shows no proceedings or order recorded for this date.
- RERA-GRG-2914-2022: Suo motu proceedings started by the Authority against the promoter, Shree Vardhman Infrahome Pvt. Ltd., for alleged violation of section 4(2)(l)(C) of the Act by not completing the Shree Vardhman Flora project within the time it declared. Status: Pending. Next hearing is listed for 16 Jan 2026. The promoter did not appear at the hearings on record, and on 18 Dec 2025 the Authority gave one more and final opportunity, warning that penal proceedings may be initiated if the promoter fails to appear and report on the project status. Latest: 18 Dec 2025, Promoter did not appear. One more and final opportunity given to appear and apprise status of project, failing which the concerned officer is to file papers to initiate penal proceedings. Matter to come up on 16 Jan 2026.
- RERA-GRG-2973-2022: Show cause notice to the promoter for not submitting a quarterly progress report, issued by the Authority on its own initiative against Shree Vardhman Infrahome Pvt. Ltd. Status: First hearing listed for 27 Jun 2022. The page records no proceedings or order for that hearing, and no order is uploaded. Latest: 27 Jun 2022, First hearing listed. Status shows FIRST HEARING, with no proceedings or order recorded.
- RERA-GRG-5127-2022: Case RERA-GRG-5127-2022 is listed between the Authority (HARERA Gurugram) and the promoter company Shree Vardhman Infrahome Pvt. Ltd. The page does not state the reason for the proceeding. Status: Listed for first hearing on 30 Jun 2022. The page shows no order uploaded. Latest: 16 Jul 2022, A document marked 'NEW COMPLAINT' was received under Dak ID 37956 and submitted on behalf of the Authority.
- RERA-GRG-5280-2019: Failure to file project information (REP-I Part A to H) online and in hard copy, and quarterly progress reports, for the registered project Shree Vardhman Flora in Sector 90, Gurugram. The Authority is considering revoking the registration certificate (No. 88 of 2017) and has decided to impose a daily penalty. Status: Pending. The next personal hearing is fixed for 24 Feb 2020 at 2.00 pm at the Authority's office in Gurugram. The case page lists the status as PENDING. Latest: 20 Jul 2020, Third notice dispatched (Sec 42 reference) and complaint dispatched on this date, according to the case page. Penalty: Rs 25,000 per day from 31 Dec 2019, for each day the default continues, up to a cumulative limit of five percent of the estimated cost of the project as determined by the Authority. The Authority has decided to impose this penalty under section 63 of the Real Estate (Regulation and Development) Act, 2016.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 14 |
|---|
| Cases | - RERA-GRG-2548-2025 (compensation, decided 03-Nov-2026): Buyer sought delay compensation for late possession; complaint dismissed because compensation for same delay was already allowed earlier.
- RERA-GRG-6173-2024 (complaint, decided 26-Nov-2025): Buyers sought delay relief on Gurugram flat; builder ordered to pay 10.85% interest, hand over possession and not charge club fees yet.
- RERA-GRG-1869-2024 (complaint, decided 09-Sep-2025): Buyer sought delay interest and conveyance after possession delay; builder ordered to pay 10.85% interest up to 18 Jun 2022.
- RERA-GRG-1982-2024 (complaint, decided 09-Sep-2025): Buyer sought delay interest and conveyance after possession delay; builder ordered to pay 10.85% interest up to 18 Jun 2022.
- RERA-GRG-3905-2023 (complaint, decided 21-Aug-2024): Buyer sought delay compensation for late flat possession; HRERA ordered 11.10% delay interest and possession within 30 days.
- RERA-GRG-5268-2022 (complaint, decided 24-Apr-2024): Buyer sought delay possession charges; builder ordered to pay 10.85% yearly interest from Nov 2015 till Jun 2022.
- RERA-GRG-4066-2021 (complaint, decided 15-Mar-2024): Buyers sought possession and delay interest; HRERA ordered builder to pay 10.85% delay interest and hand over the flat within 30 days.
- RERA-GRG-4033-2021 (complaint, decided 15-Mar-2024): Buyers sought possession and delay interest; HRERA ordered builder to pay 10.85% delay interest and hand over the flat within 30 days.
- RERA-GRG-4067-2021 (complaint, decided 15-Mar-2024): Buyers sought possession and delay interest; HRERA ordered builder to pay 10.85% delay interest and hand over the flat within 30 days.
- RERA-GRG-4061-2021 (complaint, decided 15-Mar-2024): Buyers sought possession and delay interest; HRERA ordered builder to pay 10.85% delay interest and hand over the flat within 30 days.
- RERA-GRG-7335-2022 (complaint, decided 22-Feb-2024): Buyer sought delay possession charges; authority ordered builder to pay 10.85% interest on amount paid until 22 Jun 2022 and hand over possession.
- RERA-GRG-5246-2022 (complaint, decided 22-Feb-2024): Buyer sought delay compensation for possession offered seven years late; builder ordered to pay 10.85% interest and register the conveyance deed.
- RERA-GRG-5754-2022 (complaint, decided 22-Feb-2024): Buyer sought delayed possession charges; builder ordered to pay 10.85% interest on paid amount until 11 Jun 2022.
- RERA-GRG-5243-2022 (complaint, decided 22-Feb-2024): Buyer sought delay interest and cancellation reversal after 6-year delay; builder ordered to pay 10.85% interest and cancellation quashed.
|
|---|
| Decided cases against SHREE VARDHMAN INFRAHOME PVT. LTD (all its projects) | 90 (Complaint: 72; Execution of an earlier order: 13; Compensation: 5) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in