Shree Vardhman Mantra(Resi.)/ Shopping Mart

Shree Vardhman Buildprop · Sector 67, Gurugram

Registered with RERA: Jun 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Shree Vardhman Buildprop

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSHREE VARDHMAN MANTRA(RESI.)/ SHOPPING MART
Builder (promoter)SHREE VARDHMAN BUILDPROP PVT LTD
LocationSECTOR-67,VILLAGE BADSHAPUR,G URUGRAM
RERA project IDRERA-GRG-946-2021
Registration certificate numberGGM/575/307/2022/50 DATED 13.06.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area11.262 acres
Licence69 OF 2010 DATED 11-09-2010
Estimated cost of the project₹23,511.52 lakh (₹235.12 crore)
Total units (plots, apartments, shops)1203
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered0
Units unsold when registered0
Layout plan approved on12-12-2012
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2020
Revised completion date31-12-2024
Infrastructure: projected completion31-12-2024
Infrastructure: percentage complete when registered30%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2023 (OCT-DEC)
Latest report submitted on14-Mar-2024
Quarterly reports listed on the portal6

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2023 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹299.74 lakh (₹3 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹29.79 lakh (₹0.3 crore)
Spent on construction of apartments in the quarter₹-23.55 lakh (₹-0.24 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹-178.31 lakh (₹-1.78 crore)
Project bank account (escrow): deposited in the quarter₹325.99 lakh (₹3.26 crore)
Project bank account (escrow): withdrawn in the quarter₹-201.85 lakh (₹-2.02 crore)
Project bank account (escrow): balance at quarter end₹174.11 lakh (₹1.74 crore)
Units in the project (apartments / plots)1298 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatefor 31 Dec 2023
By part
  • All towers except Tower-J: Completed and OC granted
  • Tower-J: Occupation certificate applied for
Unclear in the certificate
  • The certificate gives no percentage figures, only a status statement for the works.
  • No certificate date is stated in the document.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusPending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SHREE VARDHMAN BUILDPROP PVT LTD (all its projects)54 (Complaint: 40; Execution of an earlier order: 14)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026