Signature Global City 37D-1A

Signatureglobal Developers · Sector 37D, Gurugram

Registered with RERA: Mar 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Signatureglobal Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATURE GLOBAL CITY 37D-1A
Builder (promoter)SIGNATUREGLOBAL DEVELOPERS PRIVATE LIMITED
LocationVILLAGE - GADAULI KALAN, SECT OR-37D, GURUGRAM, HARYANA
RERA project IDRERA-GRG-1824-2024
Registration certificate numberGGM/932/664/2025/35 DATED 28.03.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/01/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.543 acres
Licence08 of 2021 dated 05.03.2021
Estimated cost of the project₹5,320.74 lakh (₹53.21 crore)
Total units (plots, apartments, shops)68
Unit sizes (carpet area, as declared)8 units of 594 sq ft carpet (2 towers); 4 units of 754 sq ft carpet (1 tower); 56 units of 817 sq ft carpet (14 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on24-03-2023
Building plans approved on23-10-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2025
Likely completion date31-01-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on23-Oct-2026
Quarterly reports listed on the portal6

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹-32.09 lakh (₹-0.32 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹94.14 lakh (₹0.94 crore)
Spent on construction of apartments in the quarter₹45 lakh (₹0.45 crore)
Spent on infrastructure in the quarter₹40.4 lakh (₹0.4 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹39.26 lakh (₹0.39 crore)
Project bank account (escrow): withdrawn in the quarter₹32 lakh (₹0.32 crore)
Project bank account (escrow): balance at quarter end₹39.38 lakh (₹0.39 crore)
Units in the project (apartments / plots)68.00 apartments, 0.00 plots
Sold in the quarter2 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Service Plans: Obtained Approval 10-04-2024
  • Electricity Plans: Obtained Approval 31-03-2021
  • Site Plans: Obtained Approval 23-10-2024
  • Building Plans: Obtained Approval 23-10-2024

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Sub structure: 100%, Excavation and raft complete; water proofing 0%. Work done in quarter: 0%
  • Super structure: 35%, Work done in quarter: 10%. Stilt/ground floor and slab status shown as yet to be started in the detail table
  • MEP - Mechanical: 0%, Work done in quarter: 0%
  • MEP - Electrical: 2%, Work done in quarter: 2%. Electrical works within flats yet to be started
  • MEP - Plumbing and Firefighting: 0%, Work done in quarter: 0%
  • Finishing - Internal: 0%, Work done in quarter: 0%
  • Finishing - External: 0%, Work done in quarter: 0%
Unclear in the certificate
  • Table A 'Building/Tower no.' field is blank, so the progress figures are not stated for a specific tower or block
  • Overall percentage of construction complete is not stated as one figure

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SIGNATUREGLOBAL DEVELOPERS PRIVATE LIMITED (all its projects)11 (Complaint: 11)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026